53 Pages

Chap07

Course: ECE 4001, Spring 2009
School: Georgia Tech
Rating:
 
 
 
 
 

Word Count: 2454

Document Preview

of Elements Project Planning Divide project into tasks, tasks into subtasks, subtasks into ... Estimate duration of each task, subtask, ... Estimate resource requirements for each task, subtask, ...(budget, personnel, facilities) Identify precedence relations among tasks 04/09/09 Chapter 7-Project Planning 1 Benefits of Project Planning Communications tool Resource allocation Benchmarking...

Register Now

Unformatted Document Excerpt

Coursehero >> Georgia >> Georgia Tech >> ECE 4001

Course Hero has millions of student submitted documents similar to the one
below including study guides, practice problems, reference materials, practice exams, textbook help and tutor support.

Course Hero has millions of student submitted documents similar to the one below including study guides, practice problems, reference materials, practice exams, textbook help and tutor support.
of Elements Project Planning Divide project into tasks, tasks into subtasks, subtasks into ... Estimate duration of each task, subtask, ... Estimate resource requirements for each task, subtask, ...(budget, personnel, facilities) Identify precedence relations among tasks 04/09/09 Chapter 7-Project Planning 1 Benefits of Project Planning Communications tool Resource allocation Benchmarking 04/09/09 Chapter 7-Project Planning 2 Keeping Engineers Busy with Multiple Projects this image is not available yet Fig. 7.1 04/09/09 Chapter 7-Project Planning 3 Stages of Engineering Design Projects Enthusiasm Disillusionment Panic Search for the guilty Punishment for the innocent Praise and honors for the nonparticipants 04/09/09 Chapter 7-Project Planning 4 Project Planning Tools Gantt Chart Critical Path Method (CPM) Program Evaluation and Review Technique (PERT) Variations and combinations of the above Many available software packages contain these tools 04/09/09 Chapter 7-Project Planning 5 Gantt Chart for Automobile Bumper Project Task N am e P r e l i m i n a r y D e s ig n B u ild P r o t o t y p e T e s t P ro to ty p e F in a l D e s ig n 1 2 3 4 5 6 7 8 9 D ays 10 11 12 13 14 15 16 17 18 26 20 21 22 23 24 25 18 37 1 0 9 Fig. 7.2 04/09/09 Chapter 7-Project Planning 6 Enhanced Gantt Chart for Automobile Bumper Project D ays Task Nam e P r e lim in a r y D e s ig n B u ild P r o t o t y p e T e s t P ro to ty p e F in a l D e s ig n h rs 1 30 20 25 40 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Fig. 7.3 04/09/09 Chapter 7-Project Planning 7 Keeping Track of Project Progress on a Gantt Chart Task N am e P r e lim in a r y D e s ig n B u ild P r o t o t y p e T e s t P ro to ty p e F in a l D e s ig n h rs 1 30 20 25 40 2 3 4 5 6 7 8 9 D ays 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Fig. 7.4 04/09/09 Chapter 7-Project Planning 8 Typical Electric Substation Fig. E7.3.1(a) 04/09/09 Chapter 7-Project Planning 9 Tasks for Designing and Building an Electric Substation Task A. Design substation B. Select site C. Prepare site D. Order transformers and related electrical equipment E. Order concrete, fencing, and related construction supplies F. Excavate for foundation G. Pour and cure concrete foundation H. Erect structural frames I. Install electrical equipment J. Erect fence K. Test electric equipment L. Connect to grid M. Clean up site 3 10 2 3 2 2 2 2 Duration (days) 10 7 3 2 2 Table E 7.3.1 04/09/09 Chapter 7-Project Planning 10 Gantt Chart for Substation Design and Construction Week 1 Task M T W Th F M A B C D E F G H I J K L M Week 2 Week 3 Week 4 Week 5 Week 6 T W Th F M T W Th F M T W Th F M T W Th F M T W Th F Fig. E7.3.1(b) 04/09/09 Chapter 7-Project Planning 11 Critical Path Method (CPM) Uses a network flow diagram to depict the precedence relations among activities (tasks) Elements of diagram are directed line segments and nodes Facilitates identification of activities whose timely completion are critical to timely completion of the project 04/09/09 Chapter 7-Project Planning 12 CPM Notation and Conventions An activity is an ongoing effort on a project task (directed line segment). Every activity has an initiating event and a closing event (nodes). Fig. 7.6 3 A (a ) A c tiv itie s (b ) E v e n ts Events consume no time. Their primary role in CPM diagrams is to separate activities. Consecutive activities must be separated by events. 04/09/09 Chapter 7-Project Planning 13 CPM Notation and Conventions (cont.) No pair of events can be directly connected by more than one activity with no intervening events. If an activity R must immediately precede S and T, the relationship is depicted as follows R S Fig. 7.7(a) T If activities R and S must both immediately precede T, the relationship is depicted as follows R T S Fig. 7.7(b) All networks must begin with a single Start event and end with a single Finish event. 04/09/09 Chapter 7-Project Planning 14 Dummy Activities Sometimes precedence relationships require the use of a dummy activity (depicted by a dashed line) to indicate the appropriate relationships. Dummy activities do not take up any time. Dummy activity is needed to correctly depict that P and Q must precede S, and P must precede R. P R Q S Dummy activity needed when several activities have same Start and End events. Activities R and S share the same Start and End events. R Fig. 7.10 S Dummy activities should be be included only when needed to display the precedence relation. 04/09/09 Chapter 7-Project Planning 15 Precedence Relations for Several Activities of Bumper Project Activity Design bracket Build bracket Build bumper Drill holes in bumper Preceded by Design bracket Build bumper, Design bracket Table 7.2 04/09/09 Chapter 7-Project Planning 16 Using Dummy Activity for Bumper Project n sig et de ac k br build bumper drill hole in bumper (a) Shows proper precedence relations for drilling the holes but does not include building the bracket build bumper drill hole in bumper (b) Improperly shows that building the bracket requires the bumper to be built first br buil ac d ke t (c) Inclusion of a dummy activity allows proper relations to be depicted n sig et de ack br Fig. 7.8 design bracket build bracket build bumper drill hole in bumper 04/09/09 Chapter 7-Project Planning 17 Multiple Dummy Activities A precedes D A and B precede E B and C precede F A D B E C F Fig. 7.9 04/09/09 Chapter 7-Project Planning 18 Project Activities and their Precedence Relations Activity A B C D E F G H I J K Duration 3 3 4 1 3 2 2 4 1 3 5 Table 7.1 Preceded by A C B, D A, B, D C, F G C E, G F, H, I 04/09/09 Chapter 7-Project Planning 19 Constructing a Network Diagram B 3 3 Start A 1 D C 4 I 1 Fig. 7.11 B 3 A E 3 J Fig. 7.12 3 F 2 3 G 2 H4 I 1 Finish Start 1 C 4 D 04/09/09 Chapter 7-Project Planning 5 K 20 Example of Constructing a Network Diagram Activity A B C D E F G H I J K L M F Preceded by A,B C A D, E, F C H D, E I, J G L, K G Table E7.4.1 A Fig. E7.4.1 D L B E C J H I K M 04/09/09 Chapter 7-Project Planning 21 Another Example of Constructing a Network Diagram* Activity Duration Preceded by A 4 B 5 C 4 A D 5 A E 6 A F 4 D,C G 7 F,B H 4 G,E A Start 4 D5 C4 E6 B 5 F4 G 7 H 4 Finish 04/09/09 Chapter 7-Project Planning 22 The Critical Path The critical path is the path of activities from the start event to the finish event for which delay in any activity along that path will delay the project finish. For projects with a small number of alternative paths, the critical path can be most efficiently identified by finding the longest of the alternative paths. 04/09/09 Chapter 7-Project Planning 23 Alternative Paths and their Length For the project depicted in Fig. 7.12 Path A-B-E-J A-B-F-G-dummy-J A-B-F-G-H-K C-D-E-J C-D-F-G-dummy-J C-D-F-G-H-K C-I-K Length 12 13 19 11 12 18 10 Table 7.3 Thus, A-B-F-G-H-K is the critical path 04/09/09 Chapter 7-Project Planning 24 Critical Path Depicted on Network Diagram B 3 A E 3 J F 2 3 3 G 2 H4 I 1 Finish Start 1 C 4 D Fig. 7.13 04/09/09 Chapter 7-Project Planning 5 K 25 Example Problem of Finding the Critical Path* Path A-E-H A-C-F-G-H A-D-dummy-F-G-H B-G-H Duration 14 23 24 16 A Start 4 D5 C4 E6 B 5 F4 G 7 H 4 Finish 04/09/09 Chapter 7-Project Planning 26 Alternate Method for Determining Critical Path This approach is more efficient for larger networks Use forward sweep to find earliest start (ES) for each activity Use backward sweep to find latest start (LS) for each activity Calculate total float (TF) for each activity TF = LS - ES Critical Path consists of Activities with TF = 0 04/09/09 Chapter 7-Project Planning 27 Earliest Start* Earliest Start (ES) is the earliest time an activity can start. It is found by tracing forward (from tail to head of each activity arrow) from the project Start event to the tail of the selected activity. When several paths are possible, use the longest path as determined by the sum of the activity durations on that path. For activity F, ES = 9 A Start 4 D5 C4 E6 B 5 F4 7 G H 4 Finish 04/09/09 Chapter 7-Project Planning 28 Project Duration* Continue until we have ES for all activities that terminate in the project Finish event. When duration of each of those activities are added to their respective ES times, the largest of the resulting sums is defined as the Project Duration. For activity H, ES=20 Project Duration =20+4=24 A Start 4 D5 C4 E6 B 5 F4 G 7 H 4 Finish 04/09/09 Chapter 7-Project Planning 29 Latest Start* Latest Start (LS) is the latest time an activity can start and still have the project completed within the Project Duration time. LS is found by tracing backwards (from head to tail of each activity) from the project Finish event to the tail of selected activity. Make sure you reach the tail of the selected activity via the head of that activity. When several paths are possible, use the longest path as determined by the sum of the activity durations on that path. The Project Duration minus the length of this longest path is the LS for the selected activity. For activity A, LS=24-24=0 A Start 4 D5 C4 E6 B 5 F4 G 7 H 4 Finish 04/09/09 Chapter 7-Project Planning 30 Total Float Total Float for each activity is the difference between the latest start and the earliest start. TF = LS - ES The activities for which TF=0 define the critical path. 04/09/09 Chapter 7-Project Planning 31 Summary of Total Float Calculations* Activity A B C D E F G H Project Duration 24 Duration ES 4 5 4 5 6 4 7 4 24 0 0 4 4 4 9 13 20 LS 0 8 5 4 14 9 13 20 TF 0 8 1 0 10 0 0 0 Critical Path consists of A-D-F-G-H 04/09/09 Chapter 7-Project Planning 32 Total Float Calculations For project shown in Fig. 7.12 Activity A B C D E F G H I J K Duration 3 3 4 1 3 2 2 4 1 3 5 19 Earliest Start 0 3 0 4 6 6 8 10 4 10 14 Latest Start 0 3 1 5 13 6 8 10 13 16 14 Total Float 0 0 1 1 7 0 0 0 9 6 0 Project Duration Table 7.4 04/09/09 Chapter 7-Project Planning 33 Example of Critical Path Determination I 10 H K 5 6 B J 2 N 5 A 1 C 3 2 G 1 E 6 F 7 L 3 M 4 O 7 D 4 Fig. E7.4.2(a) 04/09/09 Chapter 7-Project Planning 34 Summary of Example Float Calculations Activity A B C D E F G H I J K L M N O Project Duration ES 0 1 1 3 7 7 13 3 3 14 16 14 17 21 21 28 LS 0 1 4 3 7 7 13 8 12 15 17 14 17 22 21 TF 0 0 3 0 0 0 0 5 9 1 1 0 0 1 0 Table E7.4.2 04/09/09 Chapter 7-Project Planning 35 Critical Path for Example Problem I 10 H K 5 6 B J 2 N 5 A 1 C 3 2 G 1 E 6 F 7 L 3 M 4 O 7 D 4 Fig. E7.4.2(b) 04/09/09 Chapter 7-Project Planning 36 Program Evaluation and Review Technique (PERT) Based on Critical Path Method Replaces single estimate of activity duration by a probability distribution Allows estimate of probability of completing project by a specified time 04/09/09 Chapter 7-Project Planning 37 Typical Beta Distributions for Activity Durations to-optimistic estimate; the shortest time within which this activity can be completed assuming everything goes right. This is the left terminus of the pdf. tm-the most likely time required to complete the activity. This is the mode of the pdf. tp- pessimistic estimate; the longest time it will take this activity to be completed assuming everything goes wrong. This is the right terminus of the pdf. to tm tp to tm tp (a) Skewed-left Beta distribution (b) Skewed-right Beta distribution Fig. 7.14 04/09/09 Chapter 7-Project Planning 38 Network Diagram for PERT Example Problem B 2-3-4 F 1-2-7 1- A 33 E 2-3-6 J6 31- Start 11 G 1-2-4 Finish D -5 H 3-4-6 I 0-1-3 Fig. 7.15 04/09/09 Chapter 7-Project Planning 3- K 512 C 10 43- 39 PERT Procedure Calculate the expected duration te (mean) of each activity te = to + 4tm + t p 6 Calculate the variance 2 of each activity t p to 2 = 6 2 Use te to determine the expected project duration Te and identify the critical path 04/09/09 Chapter 7-Project Planning 40 Determination of Critical Path for PERT Example Calculation Activity A B C D E F G H I J K Project Duration Expected Time 3.00 3.00 4.83 1.67 3.33 2.67 2.17 4.17 1.17 3.17 5.83 21.34 Variance 0.44 0.11 1.36 0.44 0.44 1.00 0.25 0.25 0.25 0.69 2.25 Earliest Start 0.00 3.00 0.00 4.83 6.50 6.50 9.17 11.34 4.83 11.34 15.51 Latest Start 0.50 3.50 0.00 4.83 14.84 6.50 9.17 11.34 14.34 18.17 15.51 Total Float 0.50 0.50 0.00 0.00 8.34 0.00 0.00 0.00 9.51 6.83 0.00 Table 7.5 04/09/09 Chapter 7-Project Planning 41 PERT Critical Path B 2-3-4 F 1-2-7 1- A 33 E 2-3-6 J6 31- 11 G 1-2-4 H 3-4-6 Finish Start D -5 C 10 43- I 0-1-3 Fig. 7.16 04/09/09 Chapter 7-Project Planning 3- K 512 42 Probability of Completing Project by Specified time Ts Calculate the variance of the project duration as the sum of the variances of the activities on the critical path 2 2 2 2 2 2 T ( critical path )= C + D + F + G + H + K = 1.36 + 0.44 + 1.00 + 0.25 + 0.25 + 1.00 T =2.36 Use the standard normal variable z to find the probability of completing the project in a specified time Ts T Te zS= s T For Ts=20 zS = Ts Te 20 21.34 = = 0.57 T 2.36 From Table 5.1 Pr (z < -0.57) = 0.285 04/09/09 Chapter 7-Project Planning 43 Space Station PERT Problem This image is not yet available Fig. E7.5.1(a) 04/09/09 Chapter 7-Project Planning 44 Activities for Space Station PERT Problem Activity A B C D E F G H I J K Description Construct shell of module Order life support system and scientific experimentation package from same supplier Order components of control and navigational system Wire module Assemble control and navigational system Preliminary test of life support system Install life support in module Install scientific experimentation package in module Preliminary test of control and navigational system in module Install control and navigational system in module Final testing and debugging Table E7.5.1(a) 04/09/09 Chapter 7-Project Planning 45 PERT Diagram for Space Station Project D 3-3-5 25 A -3 045 G 4-5 -7 Start B 10-15-20 C -3 5 5 -2 20 F 1-1-1 K 6-8-15 8-1 J 0- 1 4 Finish H -3 2 -2 E 5-7-12 I 4-4-6 Fig. E7.5.1(b) 04/09/09 Chapter 7-Project Planning 46 Summary of PERT Calculations for Space Station Project Activity A B C D E F G H I J K Project Duration te 31.67 15.00 25.83 3.33 7.50 1.00 5.17 2.17 4.33 10.33 8.83 2 11.11 2.78 6.25 0.11 1.36 0.00 0.25 0.03 0.11 1.00 2.25 ES 0.00 0.00 0.00 31.67 25.83 15.00 35.00 35.00 33.33 37.67 48.00 56.83 LS 0.50 19.50 0.00 32.17 25.83 34.50 42.83 35.50 33.33 37.67 48.00 TF 0.50 19.50 0.00 0.50 0.00 19.50 7.83 0.50 0.00 0.00 0.00 Table E7.5.1(b) 04/09/09 Chapter 7-Project Planning 47 Another PERT Example Problem* 2. 5 D -5 - 10 A Start 2-4-8 C 2-4-8 E 3-6-12 Finish B 2.5-5-10 2-4 F -8 G 3.5-7-14 H 2-4-8 Activity A B C D E F G H Project Duration te 4.32 5.40 4.32 5.40 6.48 4.32 7.56 4.32 2 1.00 1.56 1.00 1.56 2.25 1.00 3.06 1.00 ES 0 0 4.32 4.32 4.32 9.72 14.04 21.60 25.92 LS 0 8.64 5.40 4.32 15.12 9.72 14.04 21.60 TF 0 8.64 1.08 0 10.80 0 0 0 04/09/09 Chapter 7-Project Planning 48 Probability of Completing Project by Specified time Ts* Calculate the variance of the project duration as the sum of the variances of the activities on the critical path 2 2 2 2 2 T= A + D + F + G + H = 1.00 + 1.56 + 1.00 + 3.06 + 1.00 = 2.76 Use the standard normal variable z to find the probability of completing the project in a specified time Ts T T z= s e T For Ts=30 z= Ts Te 30 25.92 = =1.48 T 2.76 From Table 5.1 Pr (z < 1.48) = 1 - Pr (z < -1.48) = 1 - 0.067 = 0.932 04/09/09 Chapter 7-Project Planning 49 CPM Diagram with Nodes Numbered 2 A B 3 4 F 2 E 3 8 J 3 3 1 Start 1 C 4 5 G 2 6 H 4 K 9 Finish D 3 I 1 7 Fig. 7.17 04/09/09 Chapter 7-Project Planning 5 50 Calendarized Version of Network Diagram 4 E 8 J dummy Start 1 A 2 B 4 F 5 G 6 H 7 K 9 Finish Start 1 C 3 D 3 I 0 2 4 6 8 10 12 14 16 18 20 Fig. 7.18 04/09/09 Chapter 7-Project Planning 51 Activity on Node Network Diagram E 4 8 A 1 4 2 B 4 F J 8 9 5 4 Start 3 1 D 3 G 6 7 H 7 K 9 Finish C I Fig. 7.19 04/09/09 Chapter 7-Project Planning 52 Refined Activity on Node Network Diagram E,3 A,3 B,3 F,2 J,3 Start D,1 G,2 H,4 K,5 Finish C,4 I,1 Fig. 7.20 04/09/09 Chapter 7-Project Planning 53
Find millions of documents on Course Hero - Study Guides, Lecture Notes, Reference Materials, Practice Exams and more. Course Hero has millions of course specific materials providing students with the best way to expand their education.

Below is a small sample set of documents:

Georgia Tech - ECE - 4001
Definition of an EngineerAn engineer is someone who can do for $1 what any fool can do for $2.04/09/09Chapter 8-Engineering Economics1Fundamental Problem of Engineering EconomicsTrade offs between initial costs and downstream costs04/09
Georgia Tech - ECE - 4001
Lecture 12 Engineering Measurements Part 1ECE 4001 L12 2008Slide #1AnnouncementsExam 1 on Monday, October 6th One sheet of handwritten notes, etc. (both sides) Lectures L1 - L6, L8 - L12 and all relevant section of Hyman assigned for readi
Georgia Tech - ECE - 4001
Lecture 13 Engineering Measurements Part 2ECE 4001 L13 2008Slide #1Outline Calculating Experimental Errors Calibration Issues Experimental Test Plan SummaryECE 4001 L13 2008Slide #2Combinations of Errors Consider additive errors
Georgia Tech - ECE - 4001
Lecture 14 Engineering Economics: Time Value of MoneyECE 4001 L14 T. Michaels 2008Slide #1AnnouncementsHW #4 Due on Wednesday Seek help if you have questions!ECE 4001 L14 T. Michaels 2008Slide #2ECE 4001 L14 T. Michaels 2008Slide #
Georgia Tech - ECE - 4001
Lecture 15 Engineering Economics: Applications and ExamplesECE 4001 L15 T. Michaels 2008Slide #1F/P P/F A/F F/A A/P P/AGradient FactorsECE 4001 L15 T. Michaels 2008Slide #2All Factors Obey Rules of AlgebraA P ( A / P )( F / P) ( P
Georgia Tech - ECE - 4001
Lecture 16 Accounting I: DepreciationECE 4001 L17 T. Michaels 2008Slide #1Salvage ValueSalvage Value = Estimated (actual) value of an item at the end of its useful life - Cost necessary to dispose of the itemECE 4001 L17 T. Michaels 2008
Georgia Tech - ECE - 4001
Lecture 17 Accounting II: Accounting PrinciplesECE 4001 L18 2008 T. MichaelsSlide #1Successful BusinessesNeed a product or service! Need to be able to price that product or service so that it will sell Need to be able to perform the service
Georgia Tech - ECE - 4001
Lecture 18 Financial AnalysisECE 4001 L19 2008 T. MichaelsSlide #1The Four Financial StatementsFinancial statements are issued on a periodic basis. These are required by US GAAP (Generally Accepted Accounting Principles) Balance Sheet In
Georgia Tech - ECE - 4001
Lecture 19 Project Planning And Management ToolsProject Planning ToolsChapter 7 Project Planning GANTT Chart CPM Chart PERT Chart (Figure 7.3) (Figure 7.12) (Figure 7.15)GANTT: Developed by Henry Gantt CPM: Critical Path Method PERT: Program Ev
Georgia Tech - ECE - 4001
ECE4001 Lecture 1 Engineering Design OverviewECE 4001 L1 2009Slide #1Handouts - Lecture 11. Lecture 1 Handout Topics Lecture Topics Objectives/Outcomes Exam Dates Syllabus2. Instructor Contact Information for ECE 4001 A. Bruno Frazier 223
Georgia Tech - ECE - 4001
ECE4001 Lecture 2 Engineering Careers for ECE/CompE GradsECE 4001 L2 2008Slide #1Course Information1. Syllabus posted on T-Square Lecture Topics Objectives/Outcomes Exam Dates2. Instructor Contact Information for ECE 4001 Bruno Frazier, P
Georgia Tech - ECE - 4001
PatentsCritical Components of Patents Patent Number Date of Patent Title Inventors Assignors Application Number Filing DateCritical Components of Patents Related Applications U.S. Patent &amp; Foreign Patent Documents Other Publications
Georgia Tech - ECE - 4001
Georgia Tech - ECE - 4001
Lecture 6 Legal Issues: Standards &amp; LiabilityPerformance vs. Design StandardsWhat is the difference between a performance standard and a design standard? All cars shall get at least 30 mpg All cars shall have seat belts Most government standards a
Georgia Tech - ECE - 4001
Lecture 6 Sustainability and Environmental IssuesSustainabilityWhat is it? Why do we care? What should we do about it?What is Sustainability? At Georgia Tech, we define sustainability research as the inventing or reinventing of a process/produc
Georgia Tech - ECE - 4001
Lecture 8 Basic Probability ConceptsNormal DistributionProbability density function for a normal distribution is given by 1P( y ) y 2e y 2 2 y2 where is the mean value of the variable y and y is the standard deviation of
Georgia Tech - ECE - 4001
Georgia Tech - ECE - 4001
Lecture 8 Statistical Models of Manufacturing Variation Process CapabilityDefine a Process Capability IndexLSLUSLDefine a process capability index: design margin CP natural variation of process USL LSL CP 6 For USL LSL 6 CP 1When C
Georgia Tech - ECE - 4001
Lecture 9 Reliability measures and prediction System reliabilitySolve this Problem:Your company has developed a new microcontroller. A lot of 1000 units are tested for 2000 hours, after which 500 good units remain. What is the is the probability t
Georgia Tech - ECE - 4001
Lecture 11 Statistical Models of Manufacturing ReliabilityECE 4001 L11 2008Slide #1Normal DistributionProbability density function for a normal distribution is given by 1P( y ) y 2e y 2 2 y2 where is the mean value of
Georgia Tech - ECE - 4001
Lecture 11 Statistical Models Of Manufacturing ReliabilityNormal DistributionProbability density function for a normal distribution is given by 1P( y ) y 2e y 2 2 y2 where is the mean value of the variable y and y is the
Georgia Tech - ECE - 4001
Georgia Tech - ECE - 4001
ECE 4001 - Project Engineering and Professional Practice October 6, 2008 Problem 1. (50 points)EXAM #1 Solutions Page 1 of 6A. (2 points) A disaster occurred at the Hyatt Regency hotel in Kansas City. This was discussed in your textbook and durin
Georgia Tech - MATH - 3012
MATH 3012 Sample Quiz Questions for Test 1, Spring 2006 WTTNote 1: There are approximately two to three times as many problems listed here as you can expect on an hour exam, but this more comprehensive version should be of greater assistance to stud
Georgia Tech - MATH - 3012
MATH 3012 Homework Problems and Solutions Chapter 2, Spring 2009, WTT and MTKNote: These problems are grouped into two categories. The rst set consists of basic problems that everyone who expects to pass the course should be able to do. The second s
Georgia Tech - MATH - 3012
MATH 3012 Homework Problems and Solutions Chapter 3, Spring 2009, WTT and MTKGroup 1: Basic Problems 1. Factor m = 2205 and n = 1925 into products of primes. Then use this factorization to nd the greatest common divisor and the least common multiple
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
University of Florida - EGM - 3401
Ain Shams University - IS - 1323
Drexel OnlineA Better U.TMMaster of Science in Software EngineeringDrexel University's College of Engineering is an internationally recognized leader in engineering education. It is the third largest private engineering college in the United Stat
Arizona - CLAS221 - CLAS221
CLAS 221 M,W,F (12-12:50) 1st Essay- Question #2Stephanie Lopez-Ramirez 3/5/08There are many examples of the theme of erotic love versus familial love throughout Ovids Metamorphoses. This concept describes the struggle a character deals when tryi
Arizona - ARH - 203
ARH 203 Field Trip Paper1/29/08I chose Skin of Earth from the exhibit El Anatsui: Gawu. The work is the length of the entire wall, about eight feet, and is about ten feet across in a rectangular shape. From afar the first thing the viewer notices
Arizona - HIST - 369
HIST 369 M,W,F (9-9:50) Chapter 53/7/08The main idea in this chapter is Mexican women coming together and uniting through their belief in the Catholic religion. The UDCM seemed to think that if the nation got back to its Catholic roots many of it
Truman State - ENGLISH - ENG307
English 307 Midterm Exam 1. In Solzhenitsyns One Day in the Life of Ivan Denisovich, I see the author showing the importance of individuality to the survival of prisons in the camp. People in the camp tend to hide their possessions. Those things belo