MGT215 Project Management 2021 1 Revision 2 1. Do the following questions? a. Your project controlling shows you actual cost of 100 and an earned value of 110. Calculate the cost performance index and explain the what the index value tell us. b. Your project controlling shows you actual cost of 350 and an earned value of 400. The planned value is 450 Calculate the schedule performance index and explain what the index value tell us. 2. The table below shows the value of a project collected for three months period