Earned Value Analysis & ReportingBased on the schedule report, the baseline time is stated to be six hundred and sixty two hourswhile the actual time is one thousand, one hundred and twelve hours, which is more than theplanned time. Therefore this means that the project is performing behind schedule and will needadditional time for it to complete.Also the baseline finish date is January 2022 however when calculated the actual finish date isDecember 2021.Also Based on the cost variance, it was stated to be (900.00). A negative value means that in