ASSIGNMENT ON PRODUCTIVITY AND PROJECT MANAGEMENT1.Carbondale Casting produces cast bronze valves on a 10-person assembly line. On a recent day,160 valves were produced during an 8-hour shift.(3 items x 5 points)a.What is their productivity?
b.John Goodale, the manager at Carbondale, changed the layout and was able to increaseproduction to 180 units per 8-hour shift. What is the new labor productivity per labor-hour?
c.What is the percentage of productivity increase?
2.Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating toproduce smaller ovens for use in high school and college kitchens. The activities necessary to buildan experimental model and related data are given in the following table:(5 items x 5 points)ACTIVITYNORMALTIME(WEEKS)CRASHTIME(WEEKS)NORMALCOST (PHP)CRASHCOST (PHP)IMMEDIATEPREDECESSOR(S)A321,0001,600-B212,0002,700-C11300300-D731,3001,600AE638501,000

Upload your study docs or become a

Course Hero member to access this document

End of preview. Want to read all 3 pages?

Upload your study docs or become a

Course Hero member to access this document

Term
Fall
Professor
N/A
Tags
Carbondale Casting, James Kimpel

Unformatted text preview: (5 items x 5 points) ACTIVITYNORMAL TIME (WEEKS) CRASH TIME (WEEKS) NORMAL COST (PHP) CRASH COST (PHP) IMMEDIATE PREDECESSOR(S) A 3 2 1,000 1,600- B2 1 2,000 2,700- C1 1 300300- D 7 3 1,300 1,600 A E 6 3 850 1,000 B F 2 1 4,000 5,000 C G 4 2 1,500 2,000 D, E H 53 2,0003,000 F, G a. Draw a Gantt Chart using the normal time. b.Draw the Activity on node (AON) network.c. Determine the critical path. d.Solve for the slack time per activity. e. Solve for the crash cost per period. f. What activities should you crash if James Kimpel wants to reduce the project time to 15 weeks? BM1710 01 Assignment 1 *Property of STI Page 1 of 2 3. A renovation of the gift shop at Orlando Amway Center has six (6) activities (in hours). For the following estimates of a, m, and b, calculate the a) expected time and the b) standard deviation for each activity: (2 items x 5 points) ACTIVITYa m b A 111519B 27 31 41C 18 18 18D 813 19 E17 18 20 F 16 19 22Expected activity time (t) = (a+4m + b) BM1710 01 Assignment 1 *Property of STI Page 2 of 2...