Chapter+4+-++2

Chapter+4+-++2 - Project Management Chapter 4 ( Continued )...

Info iconThis preview shows pages 1–8. Sign up to view the full content.

View Full Document Right Arrow Icon
Project Management Chapter 4 ( Continued )
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Activity 2 – Identify Tasks Work Breakdown Structure (WBS) – A graphical tool used to depict the hierarchical decomposition of the project into phases, activities, and tasks. Milestone – An event signifying the completion of a major project deliverable.
Background image of page 2
Activity 3 – Estimate Task Durations Elapsed time takes into consideration: Efficiency - no worker performs at 100% efficiency Coffee breaks, lunch, e-mail, etc. Estimate of 75% is common Interruptions Phone calls, visitors, etc. 10-50%
Background image of page 3

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Activity 3 – Estimate Task Durations 1. Estimate the minimum amount of time it would take to perform the task – the optimistic duration (OD). 2. Estimate the maximum amount of time it would take to perform the task – the pessimistic duration (PD). 3. Estimate the expected duration (ED) that will be needed to perform the task. 4. Calculate a weighted average of the most likely duration (D) as follows: D = (1 x OD) + (4 x ED) + (1 x PD) 6 3.33 days = (1 x 2 days) + (4 x 3 days) + (1 x 6 days) 6 PD ED OD
Background image of page 4
Activity 4 – Specify Intertask Dependencies Finish-to-start (FS)—The finish of one task triggers the start of another task. Start-to-start (SS)—The start of one task triggers the start of another task. Finish-to-finish (FF)—Two tasks must finish at the same time. Start-to-finish (SF)—The start of one task signifies the finish of another task.
Background image of page 5

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Entering Intertask Dependencies
Background image of page 6
Forward Scheduling – A project scheduling approach that establishes a project start date and then schedules forward from that date.
Background image of page 7

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Image of page 8
This is the end of the preview. Sign up to access the rest of the document.

This note was uploaded on 04/17/2008 for the course M&IS 24060 taught by Professor G.dehondt during the Spring '08 term at Kent State.

Page1 / 30

Chapter+4+-++2 - Project Management Chapter 4 ( Continued )...

This preview shows document pages 1 - 8. Sign up to view the full document.

View Full Document Right Arrow Icon
Ask a homework question - tutors are online