Exercise 17.1 cost control Key

Exercise 17.1 cost control Key - -60-240 1500 6 Roof...

Info icon This preview shows pages 1–3. Sign up to view the full content.

View Full Document Right Arrow Icon
April 11, 2016 CE 222/CEM 201 – Life Cycle Engineering and Management of Constructed Facilities Chapter 17 Cost Control Handout 1. Given the information below, complete the table and calculate Project Percent of Completion (PPC). BCAC ACWP BQAC AQWP PC(%) BCWP ECAC A A.1 100 40 105 35 = 35 / 105 = 0.333 = 33.3% = 33.3 % * 100 = 33.3 = 40 / 33.3 % = 120 A.2 50 35 77 60 = 60 / 77 = 0.780 = 78.0 % = 78 % * 50 = 39.0 = 35 / 78 % = 45 B 65 50 125 100 = 100 / 125 = 0.800 = 80% = 80 % * 65 = 52.0 = 50 / 80 % = 62.5 TOTAL 215 125 -- -- = 124.3 / 215 = 0.578 = 57.8 % = 33.3 + 39.0 + 52 = 124.3 = 120 + 45 + 62.5 = 227.5 PC i (%) = ()*+ , -)(. , ࠵?࠵?࠵?࠵? ࠵? = ࠵?࠵?࠵? (%) ∗ ࠵?࠵?࠵?࠵?࠵? ࠵?࠵?࠵?࠵? ࠵? = ࠵?࠵?࠵?࠵? ࠵? ࠵?࠵? ࠵? (%) ࠵?࠵?࠵?࠵? ࠵?࠵?࠵?࠵?࠵?࠵?࠵? = > ࠵?࠵?࠵?࠵? ࠵? , ࠵?࠵?࠵?࠵? ࠵?࠵?࠵?࠵?࠵?࠵?࠵? = > ࠵?࠵?࠵?࠵? ࠵? , PPC i (%) = ∑ -.*+ , @ ∑ -.(. , @
Image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full Document Right Arrow Icon
April 11, 2016 2. Given data below, fill out the table, calculate PPC, and determine the project status (schedule and budget) Item Total Planned BCWS ACWP Actual BCWP CV SV ECAC Budget ($) Progress ($) ($) Progress ($) 1. Excavate 9,600 100% 9600 9,000 100% 9600 600 0 9000 2. Cast Slab 1,800 100% 1800 2,000 100% 1800 -200 0 2000 3. Curb 1,500 100% 1500 1,500 100% 1500 0 0 1500 4. Walls 2,700 80% 2160 2,500 100% 2700 200 540 2500 5. Paving
Image of page 2
Image of page 3
This is the end of the preview. Sign up to access the rest of the document.

Unformatted text preview: -60-240 1500 6. Roof Trusses 1,000 40% 400 500 60% 600 100 200 833 7. Roofing 600 10% 60 0%-60 600 8. Lights 500 20% 100 250 40% 200-50 100 625 9. Seating 500 0% 0% 500 10. Paint 1,000 0% 0% 1000 Overall 20400 16100 16050 16640 590 540 20058 April 11, 2016 Calculation: Cost variance = ࠵± = ²࠵³´ − µ࠵³´ CV > 0 à Project under budget (ACWP < BCWP i.e. actual cost of the work performed is less that the budgeted cost of the performed) CV < 0 à Project over budget Schedule variance = ¶± = ²࠵³´ − ²࠵³¶ SV > 0 à Project ahead of schedule (BCWS < BCWP i.e. budgeted cost of the work scheduled is less that the budgeted cost of the performed) SV > 0 à Project behind of schedule Cost Performance index : Schedule Performance Index: BCWS: Budgeted Cost of Work Scheduled = Total Budget * Planned Progress (Scheduled Progress) (%) BCWP: Budgeted Cost of Work Performed = Total Budget *Actual Progress (%) CPI = ²࠵³´ µ࠵³´ SPI = ²࠵³´ ²࠵³¶...
View Full Document

{[ snackBarMessage ]}

What students are saying

  • Left Quote Icon

    As a current student on this bumpy collegiate pathway, I stumbled upon Course Hero, where I can find study resources for nearly all my courses, get online help from tutors 24/7, and even share my old projects, papers, and lecture notes with other students.

    Student Picture

    Kiran Temple University Fox School of Business ‘17, Course Hero Intern

  • Left Quote Icon

    I cannot even describe how much Course Hero helped me this summer. It’s truly become something I can always rely on and help me. In the end, I was not only able to survive summer classes, but I was able to thrive thanks to Course Hero.

    Student Picture

    Dana University of Pennsylvania ‘17, Course Hero Intern

  • Left Quote Icon

    The ability to access any university’s resources through Course Hero proved invaluable in my case. I was behind on Tulane coursework and actually used UCLA’s materials to help me move forward and get everything together on time.

    Student Picture

    Jill Tulane University ‘16, Course Hero Intern