ch03a - Chapter 3 The Process of Planning a Project True\/False 1 Defining resource needs is NOT necessary on small projects Answer False Response See

ch03a - Chapter 3 The Process of Planning a Project...

This preview shows page 1 - 4 out of 12 pages.

Chapter 3: The Process of Planning a Project True/False 1. Defining resource needs is NOT necessary on small projects. Response: See page 81 Level: medium 2. A representative of senior management should be invited to the project launch meeting. Response: See page 85 Level: medium 3. The primary purpose of the launch meeting is to develop the project plan and budget. Response: See pages 85 and 86 Level: medium 4.When planning, it is best for the project manager to breakdown and define the different levels of the project plan. Response: See page 87 Level: medium 5. The initial project meeting is just to coordinate the project, so areas of responsibility do NOT need to bediscussed. Response: See page 85 Level: medium
6. The project plan should begin with a complete description of all agreements made with the client or any third party. Response: See page 80 Level: medium 7. As a rule of thumb, the lowest level tasks in a typical project should NOT take longer than two days to complete. Response: See page 87 Level: medium 8. The start and finish date of a project must be specified before the action plan can be completed. Response: See page 93 Level: medium 9. Procedures for monitoring, collecting, and storing data on project performance should be discussed in the Schedules section of the project master plan. Response: See page80 Level: medium 10. The details of the project work force are discussed in the Resource Requirements section of the project master plan. Response: See page 81 Level: medium 11. It is acceptable to restrict the launch meeting to brainstorming a problem. Response: See page 85 Level: medium
12. The action plan should identify the project’s deliverable. Response: See page 87 Level: easy 13. It is NOT possible to overdo it when it comes to project planning. Response: See page 79 Level: medium 14.Predecessors must be listed in the WBS because they are critical for scheduling. Response: See page 90 Level: easy 15. Lack of planning is a major contributor to project’s failure. Response: See page 79 Level: medium 16. You can depict who is responsible for a task on a RACI. Response: See pages 97 Level: medium

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture