exam4 - MA 103 1. Consider the digraph of jobs: A(3) C(5)...

Info iconThis preview shows page 1. Sign up to view the full content.

View Full Document Right Arrow Icon
MA 103 QUIZ 4 1. Consider the digraph of jobs: A(3) C(5) E(8) F(2) a) What is the length of the critical path for the project? b) Schedule the jobs on two processors using the priority list ABCDEF c) Schedule the jobs on two processors using the critical path algorithm 2. Schedule the independent jobs