Question 7Which of the following is true about revenue variances?1 pointCan only be calculated in single product scenariosOnly are calculated using budgeted sales priceCan be calculated in multi-product scenariosAre more important than cost variances
8Question 8Which of the following is true about revenue variances?1 point
View full document
Question 1Marbles Company has the following information available regarding itslabor:Managers expected to pay $11 per direct labor hour, but ended up paying$10 per labor hour. Each unit produced should take 1 direct labor hour;actual total usage was 990 direct labor hours. Finally, the companyplanned to produce 1,000 units, but only produced 950.Calculate the labor spending variance.
View full document