BUS ADM 748 HW 3 2A 2B Path 1: A-B-E-H-K = 2+2+2+2+2=10 Days Path 2: A-C-F-H-K= 2+3+3+2+2= 12 Days Path 3: A-D-G-J-K = 2+4+6+1+2= 15 Days Path 4: A-C-F-I-J-K = 2+3+3+5+1+2 = 16 Days 2C Critical path is path 4, since it is the longest path. 2D Shortest path is path 1 at 10 days.
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full Document Right Arrow Icon
BUS ADM 748 HW 3 3A 3B Path 1: A-E-J 10+8+12=30 Path 2: A-E-I-K-L 10+8+6+8+10=42 Path 3: A-D-F-G-J