Exercises of Project Management 2015.doc - Exercises of Project Management Problem 1 assignment Given the following Time Chart and Network Diagram find

Exercises of Project Management 2015.doc - Exercises of...

This preview shows page 1 - 3 out of 4 pages.

Exercises of Project Management Problem 1: assignment Given the following Time Chart and Network Diagram, find the Critical Path using ES-EF & LS-LF algorithm. Activity a m b t Variance A 2 3 4 B 1 2 3 C 4 5 12 D 1 3 5 E 1 2 3 Problem 2: A project has an expected completion time of 40 weeks and a standard deviation of 5 weeks. It is assumed that the project completion time is normally distributed. (a) What is the probability of finishing the project in 50 weeks or less? (b) What is the probability of finishing the project in 38 weeks or less? (c) The due date for the project is set so that there is a 90% chance that the project will be finished by this date. What is the date?
Image of page 1
Problem 3: assignment Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this project are listed in the table below along with their costs and completion times in weeks.
Image of page 2
Image of page 3

You've reached the end of your free preview.

Want to read all 4 pages?

  • Winter '20

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture

Stuck? We have tutors online 24/7 who can help you get unstuck.
A+ icon
Ask Expert Tutors You can ask You can ask You can ask (will expire )
Answers in as fast as 15 minutes