Module 4 Exam Here is your test result.The dots represent the choices you have made. The highlighted questions are the questions you have missed. Remediation Accessed shows whether you accessed those links.'N' represents links not visited and 'Y' represents visited links. Back to Status pagecontains 21 Questions1) Each event detailed in the Integrated Master Plan (IMP) needs to be broken down into which of the following in the Integrated Master Schedule (IMS)? [4.2.1 - Relate the relationship of the Integrated Master Plan (IMP) to the Integrated Master Schedule (IMS).][Remediation Accessed :N] TasksCriteriaMilestonesWork packages2) In which step of the Schedule Development and Management Process do you describe all the tasks and activities that must be completed to achieve program objectives? [4.3.1 - Select the six steps for the schedule development and management process.]Identify Tasks Sequence Tasks Construct Schedules Determine Resource Requirements 3) Looking at a program's task list, you realize that the "Preliminary Design" task cannot start until a vendor has been selected. This is an example of which type of task dependency? [4.3.2 -Given a task relationship scenario, identify the standard type of dependencies or relationships between schedule activities.]Finish-to-Start (FS) Finish-to-Finish (FF)Start-to-Start (SS)Start-to-Finish (SF)Page 1 of 6DAU10/25/2018
4) What is the result of the Identification of Schedule Tasks step in the Schedule Development and Management Process? [4.3.3 - Identify the end result of the identification of schedule tasks step.][Remediation Accessed :N]
5) Which schedule duration estimating method considers the optimistic estimate, the pessimistic estimate, and the most likely estimates? [4.3.4 - Using a task duration estimating calculation, select the correct estimating technique.]Three-Point EstimateParametric EstimateSingle-Point EstimateAnalogous Estimate6) What is the difference between a summary schedule and an intermediate schedule? [4.3.5 Identify the differences in schedules produced, as an output of constructing program schedules.]Summary schedules graphically depict the contractually required events and milestones to accomplish program objectives; whereas intermediate schedules tie, or roll up, the detailed tasks in the detailed schedules to key events and milestones in the summary schedule(s).Summary schedules tie, or roll up, the detailed tasks in the detailed schedules to key events and milestones in the summary schedule(s); whereas intermediate schedules graphically depict the contractually required events and milestones to accomplish program objectives.Summary schedules graphically depict the effort at the work package and planning package -

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture