CONFIDENTIAL CONFIDENTIAL UNIVERSITI TUN HUSSEIN ONN MALAYSIA FINAL EXAMINATION SEMESTER I SESSION 2012/2013 ANSWERS SCHEME SUBJECT : CONSTRUCTION PROJECT MANAGEMENT CODE OF SUBJECT : BPE 4442/ BPE 44402 COURSE : 4 BPD DATE : DECEMBER/ JANUARY DURATION : 2 HOURS INSTRUCTION : ANSWER ALL QUESTIONS THIS QUESTION PAPER CONSISTS OF THREE (3) PAGES
Image of page 1
BPE 4442 / BPE 44402 “The Tender shall remain open for a period of Hundred Eighty (180) daysfrom the finaldate for submission of Tenders stipulated in the Tender Notice or such period as may beextended by the Superintending Officer. The successful Tenderer will be notified of theTender Board’s decision within this period and no Tenderer may withdraw his Tenderwithin this period.”(a)Explain the meaning of Tender Validity Period. (5 marks) (b)Discuss how long exactly the validity period as mentioned by the Clause. (c)Discuss the scenario that may happen upon the lapse of Hundred Eighty (180)days period. (10 marks)
Image of page 2
Image of page 3

You've reached the end of your free preview.

Want to read all 6 pages?

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture