Unit 5 IP MATH 451The __________ is the square root of the project variance.oactivity standard deviationoproject time estimateostandard deviation of the projectoactivity variance
Z is the number of __________ the target completion time lies from the expected completion time.
For a project with an expected completion time of 15 weeks, a target completion of 18 weeks, and project standard deviation of 1.95 weeks, Z-score is ____.
Managers are interested in speeding up the project __________.
If the A-B-D is the critical path for this project, the estimated completion time is _____ weeks.