Project Human Resource Management Lecture # 5 MPM- By Farhat Fatima
Image of page 1
Estimate Activity Resources
Image of page 2
Estimate Activity Resources Estimate Activity Resources is the process of estimating team resources and the type and quantities of materials, equipment, and supplies necessary to perform project work. The key benefit of this process is that it identifies the type, quantity, and characteristics of resources required to complete the project.
Image of page 3
This process is performed periodically throughout the project as needed. The Estimate Activity Resources process is closely coordinated with other processes, such as the Estimate Costs process.
Image of page 4
ESTIMATE ACTIVITY RESOURCES: INPUTS 1. PROJECT MANAGEMENT PLAN Resource management plan The resource management plan defines the approach to identify the different resources needed for the project. It also defines the methods to quantify the resources needed for each activity and aggregates this information. Scope baseline The scope baseline identifies the project and product scope necessary to meet the project objectives. The scope drives the needs for both team and physical resources.
Image of page 5
2. PROJECT DOCUMENTS Activity attributes Activity attributes provide the primary data source for use in estimating team and physical resources required for each activity on the activity list.
Image of page 6
Image of page 7