Probability of Project Completion For a project, Z was calculated as 0.35, the probability of the target completion is __________. 63% 63.31% 63.68% or 64% 35%
The target completion time for a project with an expected completion time of 13 weeks and project standard deviation of 1.15 is __________ with a 90% certainty.
PERT makes the assumption that __________.
The variance of the complete project is computed by summing the variances of the activities on the __________.
Z is the number of __________ the target completion time lies from the expected completion time.
weeks variances standard deviations distributions
Given the following activities for a project, with the critical activities in red,