
Unformatted text preview: Building Professional in Project Management. TM MENA Chapter PMI MENA CHAPTER
Chairman PMI MENA Chapter:
Dr. Gamal Nassar
gamal_nassar_cec @yahoo.com
Education & Certification : Eng. Suzanne Bedier Tech. Manager (Mterial Development, Evaluation & Exams): Eng.
Amal Ismail •Contact Adminstration :
•[email protected]
•[email protected] 7 Lebanon St, ElEl-Mohandseen Giza
TeleFax:
TeleFax: +3461062 & 3461046
Mob: +0127448007 & 0106986614 Building Professional in Project Management. TM MENA Chapter Monitoring & Controlling
Process Group 7 Lebanon St, ElEl-Mohandseen Giza
TeleFax:
TeleFax: +3461062 & 3461046
Mob: +0127448007 & 0106986614 Develop
Project
Management
Plan Scope
Planning Scope
Definition Activity
Definition 5.1 5.2 6.1 4.3 Activity
Resources
Estimating
6.3 Create WBS
5.3
Risk
Management
Planning
11.1 Develop
Project
Charter
4.1 Risk
Identification
11.2 Develop
Preliminary
Project
Scope
Statement
4.2 Activity
Duration
Estimating
6.4 Cost
Estimating
7.1 Cost
budgeting
7.2 Qualitative
Risk
Analysis
11.3 Perform
Quality
Assurance
8.2 Develop
Project Team
9.3 Information
Distribution
10.2 Request
Seller
Responses
12.3 Select Sellers
12.4 4.4 Human
Resource
Planning Schedule
Development
6.5 9.1 Quantitative
Risk
Analysis
11.4 Direct and
Manage
Project
Execution Activity
Sequencing
6.2 Acquire
Project Team
9.2 Quality
Planning
8.1 Risk
Response
Planning
11.5 Communications
Planning
10.1
Plan
Purchases and
Acquisitions
12.1 Scope
Verification
5.4 Scope
Control Schedule
Control 5.5 6.6 Plan
Contracting
12.2 Close
Project
4.7 Monitoring and
Controlling Project Work Integrated Change
Control Contract
Closure 4.5 4.6 12.6 Cost Control
7.3 Perform
Quality
Control 8.3 Manage
Project
Team 9.4 1-<#> Performance
Reporting
10.3 Mange
Stakeholders
10.4 Risk
Monitoring
and Control
11.6 Contract
Administration
12.5 ٣ PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP 1-<#>
Slide No.٤ PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP 1-<#>
Slide No.٥ PMP
PMP
PMP
PMP Planning & Control Cycle PMP
PMP
PMP
PMP
PMP Objectives PMP Corrective Actions PMP
PMP
PMP Planning PMP
PMP
PMP
PMP Execution PMP
PMP
PMP
PMP
PMP Results PMP Slide No.٦ 1-<#> Follow up &
Monitoring PMP PMP
PMP
PMP
PMP
PMP
PMP Monitoring & Controlling Processes PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP The Monitoring & Controlling Processes performed to
observe project execution so that potential problems
can be identified in a timely manner and corrective
action can be taken (when necessary), to control the
execution of the project PMP
PMP
PMP
PMP
PMP
PMP Slide No.٧ PMP
PMP
PMP
PMP
PMP
PMP Monitoring & Controlling Processes PMP
PMP
PMP
PMP The key benefits of this process group are: PMP
PMP
PMP
PMP • Project performance is observed and measured regularly
to identify variances from the project management plan. PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP • Provide feedback between project phases to implement
corrective or preventive actions to bring the project into
compliance with the project management plan.
• Monitor and control the work being done as well as the
entire project effort.
Slide No.٨ PMP
PMP
PMP
PMP
PMP
PMP Monitoring & Controlling Processes PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP The Monitoring & Controlling Processes includes:
• Monitoring the ongoing project activities against the
project management plan and the project performance
baseline
• Influencing the factors that could circumvent integrated
change control so only approved changes are
implemented PMP
PMP
PMP
PMP Slide No.٩ PMP
PMP
PMP
PMP Monitor & Control Project work PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP The Monitor & Control Project work process is concerned with:
• Comparing actual project performance against the project
management plan.
• Assessing performance to determine whether any corrective or
preventive actions are indicated and then recommending those
actions as necessary.
• Analyzing, tracking, and monitoring project risks.
• Providing information to support status, progress, and forecast
reports.
• Monitoring implementation of approved changes when and as
they occur.
Slide No.١٠ PMP
PMP
PMP Establishing Performance
Measurements PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP z Performance Reporting involves collecting and reporting
information regarding project progress and project
accomplishments to:
¾ Stakeholders
¾ Project Team Members
¾ Management Team
z Reporting might include information concerning project
Quality, Cost, Scope, Project Schedule, Procurement, and
Risk. PMP Slide No.١١ PMP
PMP
PMP
PMP Performance Reporting PMP
PMP
PMP
PMP
PMP There are five tools and techniques in this process: PMP 9 Performance Review PMP
PMP 9 Variance analysis PMP
PMP 9 Trend analysis PMP
PMP 9 Earned Value analysis PMP
PMP 9 Information Distribution PMP
PMP
PMP
PMP
PMP
PMP Slide No.١٢ PMP
PMP
PMP Performance Reporting PMP
PMP continue
continue PMP
PMP
PMP
PMP
PMP z Performance Review PMP Performance reviews are project status meetings held
with the project team and stakeholders to collect status
and report on project progress. PMP
PMP
PMP
PMP
PMP
PMP z Variance Analysis
Variance analysis compares the expected project plan
results with the actual results as the project progress to
determine if variance exist PMP
PMP
PMP
PMP
PMP
PMP
PMP Slide No.١٣ PMP
PMP
PMP
PMP C/SCSC PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP ost & SSchedule
chedule C
ontrol SSystem
ystem C
riteria
C
Cost
Control
Criteria PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP Slide No.١٤ PMP
PMP
PMP
PMP C/SCSC PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP BAC
BCWS = PV
BCWP = EV
ACWP = AC
EAC
ETC
CPI
CV
SPI
SV
CVP
SVP
Slide No.١٥
:
:
:
:
:
:
:
:
:
:
:
: Budget At Completion
Budget Cost Work Schedule
Budget Cost Work Performed
Actual Cost Work Performed
Estimated Cost At Completion
Estimated Cost to Complete
Cost Performed Index
Cost Variance
Schedule Performed Index
Schedule Variance
Cost Variance %
Schedule Variance % PMP Performance Measurement PMP
PMP
PMP Cost PMP
PMP EAC PMP
PMP VA C ETC
BAC PMP
PMP ACWP PMP CV PMP SV BCWS PMP BCWP PMP
PMP Projected
Schedule
Slippage
(at completion) Schedule
Slippage
(to date) PMP
PMP Time Key: PMP
PMP Data Date PMP
PMP
PMP
PMP
PMP Slide No.١٦ BCWS (PV): Budget Cost of Works Scheduled
BCWP (EV): Budget cost of Works Performed
ACWP (AC): Actual Cost of Works Performed
SV: Schedule Variance
CV: Cost Variance
ETC: Estmitae to Complete
BAC: Budget At Completion
EAC: Estimate At Completion (LRE- Lasted Revised Estimate)
VAC: Variance At Completion PMP
PMP
PMP
PMP Earned Value Terms PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP Data Element Term Acronym Scheduled Work Planned Value PV Earned Value Earned Value EV Actuals Actual Cost AC Authorized Work Budget at Completion BAC Forecasted Cost Estimate at Completion EAC Work Variance Schedule Variance SV Cost Variance Cost Variance CV Completion Variance Variance at Completion VAC PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP Slide No.١٧ 1-<#> PMP
PMP
PMP
PMP Planned Value (PV) PMP
PMP
PMP
PMP
PMP Work schedule to be accomplished PMP
PMP Performance Measurement Baseline PMP
PMP
PMP
PMP 80000 60000 PMP 50000 PMP 40000 PMP 30000 PMP 20000 PMP 10000 PMP
PMP BAC 70000 PV CURRENT PMP PV JANUARY
FEBRUARY
MARCH
APRIL
MAY
JUNE
JULY 0
JANUARY PMP FEBRUARY MARCH APRIL MAY 1-<#>
Slide No.١٨ JUNE JULY 0
2500
8000
13000
42000
62000
70700 PMP
PMP
PMP
PMP Earned Value (EV) PMP
PMP
PMP
PMP
PMP
PMP Budgeted value of completed or in-process work PMP
PMP
PMP 80000 PMP 70000 PMP 60000 CURRENT Perf ormance Measurement Baseline BCWS
JANUARY
FEBRUARY
MARCH
APRIL
MAY
JUNE
JULY PMP
PMP
PMP
PMP
PMP 50000 BCWS BCWP 40000 30000 20000 PMP
PMP
PMP 10000 0
JANUARY PMP FEBRUARY MARCH APRIL MA Y 1-<#>
Slide No.١٩ JUNE JULY 0
2500
8000
13000
42000
62000
70700 BCWP
0
3600
8000
10000
38000 PMP
PMP
PMP
PMP Actual Cost (AC) PMP
PMP
PMP
PMP
PMP
PMP Actual expenditures for completed or in-process work. PMP
Performance Measurement Baseline PMP
80000 PMP 70000 PMP 60000 CURRENT PMP PMP
PMP
PMP 40000 PMP 30000 PMP ACWP 50000 BCWS
JANUARY
FEBRUARY
MARCH
APRIL
MAY
JUNE
JULY BCWS
BCW 20000 PMP
PMP
PMP
PMP 10000 0
JANUARY FEBRUARY MARCH APRIL 1-<#>
Slide No.٢٠ MAY JUNE JULY 0
2500
8000
13000
42000
62000
70700 BCWP
0
3600
8000
10000
38000 ACWP
0
6000
8000
8000
48000 PMP
PMP
PMP
PMP Schedule Variance PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP z Comparing the EV, the amount originally
budgeted for the work that has been completed
or is in-process, to the PV, the amount
budgeted for the work that was planned to have
been accomplished
z SV = EV – PV
z A negative result means less work has been
performed than was planned PMP
PMP Slide No.٢١ PMP
PMP
PMP
PMP SV Example PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP z PV = $42,000
z EV = $38,000
z AC = $48,000 PMP
PMP
PMP z SV = EV – PV
= $38,000 – $42,000 = - $4,000 PMP
PMP
PMP
PMP
PMP
PMP z SV% = SV / PV
= - $4000 / $42,000 = - 0.095 PMP = - 9.5% PMP Slide No.٢٢ PMP
PMP
PMP
PMP Cost Variance PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP z Comparing the amount originally budgeted for
the work completed or in-process, the EV, to
the actual costs of that work, the AC
z CV = EV – AC
z A negative CV means more dollars were spent
to accomplish the work than was planned PMP
PMP
PMP
PMP
PMP
PMP Slide No.٢٣ PMP
PMP
PMP
PMP
PMP Cost Variance Example PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP z PV = $42,000
z EV = $38,000
z AC = $48,000 PMP
PMP
PMP z CV = EV - AC
= $38,000 – $48,000 = - $10,000 PMP
PMP
PMP
PMP z CV% = CV / EV PMP = - $10,000 / $38,000 PMP = - 26% PMP
PMP Slide No.٢٤ PMP
PMP
PMP
PMP Performance Indices PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP z Dfn: Cost- and schedule-performance
efficiency calculations; expressed in $ PMP – Cost Performance Index (CPI) PMP
PMP • CPI = EV/AC PMP
PMP
PMP – Schedule Performance Index (SPI) PMP
PMP • SPI = EV/PV PMP
PMP
PMP
PMP Slide No.٢٥ PMP
PMP
PMP
PMP CPI Example PMP
PMP
PMP
PMP z PV = $42,000 PMP
PMP z EV = $38,000 PMP
PMP z AC = $48,000 PMP
PMP z CPI = EV / AC PMP
PMP = $38,000 / $48,000 = 0.79 PMP
PMP
PMP z $0.79 worth of work was actually done for each
$1.00 spent PMP
PMP
PMP
PMP
PMP Slide No.٢٦ PMP
PMP
PMP
PMP SPI Example PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP z PV = $42,000
z EV = $38,000
z AC = $48,000 PMP
PMP z SPI = EV / PV PMP = $38,000 / $42,000 = 0.90 PMP
PMP
PMP
PMP
PMP z $0.90 worth of work has been done for each $1.00 worth
of work that was planned to be done PMP
PMP
PMP Slide No.٢٧ PMP
PMP
PMP
PMP Estimate at Completion (EAC) PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP z Def: The management’s assessment of the
cost of the project at completion PMP – After variance analysis, the estimated cost at PMP
PMP
PMP completion is determined PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP Slide No.٢٨ PMP
PMP
PMP
PMP EAC Calculations PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP z An EAC is a forecast of the most likely total value
based on project performance and risk quantification.
z EAC is the projected or anticipated total final value for
a schedule activity, WBS component, or project when
the defined work of the project is completed.
z One EAC forecasting technique is based upon the
performing organization providing an estimate at
completion: PMP
PMP
PMP
PMP Slide No.٢٩ PMP
PMP
PMP
PMP EAC Calculations PMP “continue”
continue” PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP z EAC using a new estimate. EAC equals the
actual costs to date (ACC) plus a new ETC that
is provided by the performing organization.
z This approach is most often used when past
performance shows that the original estimating
assumptions were fundamentally flawed or that
they are no longer relevant due to a change in
conditions.
z Formula: EAC = ACC + ETC PMP
PMP Slide No.٣٠ PMP
PMP
PMP
PMP EAC Calculations PMP “continue”
continue” PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP z The two most common forecasting techniques for
calculating EAC using earned value data are some
variation of:
z EAC using remaining budget. EAC equals ACC plus the
budget required to complete the remaining work, which
is the budget at completion (BAC) minus the earned
value (EV). This approach is most often used when
current variances are seen as atypical and the project
management team expectations are that similar
variances will not occur in the future. Formula:
EAC = ACC + BAC – EV PMP
PMP Slide No.٣١ PMP
PMP
PMP
PMP EAC Calculations PMP “continue”
continue” PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP z EAC using CPIC. EAC equals actual costs to date
(ACC) plus the budget required to complete the
remaining project work, which is the BAC minus the
EV, modified by a performance factor (often the CPIC).
This approach is most often used when current
variances are seen as typical of future variances.
Formula: EAC = ACC + ((BAC – EV) / CPIC)
z Each of these approaches can be the correct approach
for any given project and will provide the project
management team with a signal if the EAC forecasts
are not within acceptable tolerances. PMP
PMP Slide No.٣٢ PMP
PMP
PMP
PMP EAC Example PMP
PMP
PMP
PMP
PMP z One methodology: PMP – EAC = BAC / CPI PMP
PMP – BAC = $80,000 PMP
PMP – CPI = 0.79 PMP
PMP – EAC = $80,000 / 0.79 = $101,265 PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP Slide No.٣٣ PMP
PMP
PMP
PMP Variance at Completion PMP
PMP
PMP
PMP
PMP
PMP
PMP z BAC = $80,000
z EAC = $101,265 PMP
PMP
PMP z VAC = BAC – EAC = $80,000 – $101,265 PMP
PMP
PMP = - $21,265 PMP
PMP
PMP
PMP
PMP z Based on past performance, project will exceed
planned budget by $21,265 PMP
PMP Slide No.٣٤ PMP
PMP
PMP
PMP Earned Value Examples PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP PV EV AC $1 $1 $1 On schedule On cost $2 $2 $1 On schedule Under cost $1 $1 $2 On schedule Over cost $1 $2 $2 Ahead of schedule On cost $1 $2 $3 Ahead of schedule Over cost $1 $2 $1 Ahead of schedule Under cost $3 $2 $1 Behind schedule Under cost $2 $1 $3 Behind schedule Over cost $2 $1 $1 Behind schedule On cost Slide No.٣٥ PMP
PMP
PMP
PMP Sample Cost Problem PMP
PMP
PMP
PMP
PMP BAC
BAC ==$$40k
40k zz
EV
EV==$$20k
20k zz PMP
PMP
PMP PV
PV==$$28k
28k zz
AC
AC==$$26k
26k zz PMP
PMP
PMP Calculate
Calculate
%
%of
ofWork
WorkScheduled
Scheduled
%
%of
ofBudget
BudgetSpent
Spent
%
%of
ofWork
WorkAccomplished
Accomplished
Cost
CostVariance
Variance
Schedule
ScheduleVariance
Variance PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP Slide No.٣٦ PMP
PMP
PMP
PMP Sample Solution PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP Calculate
z % of Work Scheduled PV / BAC = $ 28K / $ 40K = 70 %
z % of Budget Spent z % of Work Accomplished EV / BAC = $ 20K/$ 40K= 50 PMP
PMP
PMP
PMP
PMP AC / BAC = $ 26K / $ 40K = 65 % z Cost Variance EV – AC = $ 20K – $ 26K = - $ 6K z Schedule Variance EV – PV = $ 20K – $ 28K = - $ 8K PMP
PMP Slide No.٣٧ PMP
PMP
PMP
PMP Scope Verification PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP The Scope Verification is the process of
obtaining the stakeholders’ formal acceptance
of the completed project scope and associated
deliverables.
Verifying the project scope includes reviewing
deliverables to ensure that each is completed
satisfactorily. PMP
PMP
PMP
PMP Slide No.٣٨ PMP
PMP
PMP
PMP Scope Verification PMP
PMP
PMP
PMP
PMP
PMP
PMP Scope Verification PMP Quality Control PMP
PMP Is primary concerned with PMP
PMP
PMP
PMP Acceptance PMP Correctness PMP
PMP The work results PMP
PMP
PMP Slide No.٣٩ PMP
PMP
PMP
PMP
PMP
PMP Manage Project Team PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP z Manage Project Team involves tracking team
member
performance,
providing
feedback,
resolving issues, and coordinating changes to
enhance project performance. PMP
PMP
PMP
PMP z Observe team behavior, manage conflict, resolve
issues, and appraise team member performance PMP
PMP
PMP
PMP Slide No.٤٠ PMP
PMP
PMP Manage Project Team
Tools & Techniques PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP Issue Log
z Document persons responsible for resolving
specific issues by a target date.
z Help the project team monitor issues until
closure.
z Address obstacles that can block the team from
achieving its goals. PMP
PMP
PMP
PMP
PMP Slide No.٤١ PMP
PMP
PMP
PMP Contract Administration PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP The contract administration process ensures that the seller’s
performance meets contractual requirements and that the
buyer performance goes according to the terms of the
contract. PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP Contract Administration includes the application of :
– Direct and manage Project Execution.
– Performance reporting to monitor contractor cost, schedule,
and technical performance.
– Perform Quality Control
– Integrated Change Control
– Risk Monitoring and Control.
Slide No.٤٢ PMP
PMP
PMP Contract Administration :
Tools & Techniques PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP Payment System
The payment system includes appropriate reviews and approvals
by project management team, and payments are made in
accordance with the terms of the contract. PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP Claims Administration
If the buyer and seller cannot agree on compensation, It may hav
e
have
to be handled in accordance with the dispute resolution
procedures established in the contract. Records Management System
The system is used to maintain an index of contract documents
and correspondence, and assist with retrieving and archiving tha
thatt
documentation. PMP Slide No.٤٣ PMP
PMP
PMP
PMP Contract Administration : Outputs PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP Organizational Process Assets (Updates)
z Correspondence: Complete and accurate written record of all written and
oral contract communications, as well as actions taken and decisions made.
z Payment Schedules and requests: This assumes that the project is using an
external payment system.
z Seller performance evaluation documentation: z Prepared by the buyer, document the seller’s ability to continue
to perform work on the current contract.
z Indicate if the seller can be allowed to perform work on future
projects or rate how well the seller is performing.
z These documents can form the basis for early termination of the
seller’s contract.
Slide No.٤٤ PMP
PMP
PMP
PMP
PMP Manage Stakeholders PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP Managing communications to satisfy the
needs of, and resolve issues with, PMP
PMP
PMP project stakeholders PMP
PMP
PMP
PMP Project Manager … PMP responsible for stakeholder management PMP
PMP
PMP Slide No.٤٥ PMP
PMP
PMP
PMP Union
Union PMP Vendor
Vendor PMP
PMP
PMP
PMP
PMP
PMP
PMP Client
Client PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP Contractor
Contractor PMP
PMP
Sponsor
Sponsor
PMP Slide No.٤٦ 1-<#> PMP
PMP
PMP
PMP
PMP Manage Stakeholders PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP Actively managing stakeholders:
• Increase the probability that the project will not veer
off track due to unsolved issues
• Enhance the ability of persons
synergistically
• Limits disruptions during the project PMP
PMP
PMP
PMP
PMP Slide No.٤٧ to operate PMP
PMP
PMP
PMP
PMP Manage Stakeholders PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP Communications Management Plan :
Stakeholder requirements and expectations provide
an understanding of stakeholder goals, objectives,
and level of communication during the project
The needs and expectations are identified, analyzed,
and documented in the communication management
plan. PMP
PMP
PMP Slide No.٤٨ PMP
PMP
PMP
PMP
PMP Manage Stakeholders PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP
PMP Issue Logs :
Document and monitor the resolution of issues
An issue is clarified and stated in a way that it
can be resolved.
An owner is assigned and a target date is
usually established for closure.
Unso...
View
Full Document