Step 1: Activities Estimated time of completion in days Choose a specific date for wedding 3 Comprise information to develop a budget 21 Decide on number of attendees 8 Choice of theme 15 Create a seating chart for guests 10 Select caterer and vendor 21 Choose baker and cake 3 Choose wedding dress 17 Get bridesmaids dresses and grooms tux 14 Choose and reserve honeymoon 9 Choose between live band or DJ 6 Book Band or DJ 7 Rehearsal 7 Step 2: Activity Estimated time Early Start Late Start Early Finish Late Finish Choose a specific date for wedding 3 0 0 3 3
Image of page 1
Comprise information to develop a budget 21 4 4 25 25 Decide on number of attendees 8 14 26 22 34 Choice of theme 15 22 35 45 49 Create a seating chart for guests 10 45 50 55 60 Select caterer and vendor 21 55 61 78 82 Choose baker and cake 3 78 83 81 86 Choose wedding dress 17 81 87 98 104 Get bridesmaids dresses and grooms tux 14 98 105 112 119 Choose and reserve honeymoon 9 112 120 121 129 Choose between live band or DJ 6 121 130 127 136 Book Band or DJ 7 127 137 134 144 Rehearsal 7 134 145 141 152 The critical path is highlighted in color. This path is from top to bottom and is dependent
Image of page 2
Image of page 3

You've reached the end of your free preview.

Want to read all 3 pages?

Unformatted text preview: on time constraints based on when the wedding is set. 28 days of slack is left just in case the wedding date offsets the time given to create wedding. If only the critical parts are hit it would take 98 days to plan the wedding leave a little of 3 months of slack to work with. This gives enough time to work out any issues that may arise from issues that could occur. Meet the critical path is important in order for the wedding to still occur on time. By hitting each task, it will allow the wedding to occur no matter the situation while still having available time to make adjustments if needed. If tasks are delayed the float days acquired can be used to mitigate lost time. If the project falls behind, then at one point a certain part of the project needs to be rushed or shortened....
View Full Document

  • Spring '17

What students are saying

  • Left Quote Icon

    As a current student on this bumpy collegiate pathway, I stumbled upon Course Hero, where I can find study resources for nearly all my courses, get online help from tutors 24/7, and even share my old projects, papers, and lecture notes with other students.

    Student Picture

    Kiran Temple University Fox School of Business ‘17, Course Hero Intern

  • Left Quote Icon

    I cannot even describe how much Course Hero helped me this summer. It’s truly become something I can always rely on and help me. In the end, I was not only able to survive summer classes, but I was able to thrive thanks to Course Hero.

    Student Picture

    Dana University of Pennsylvania ‘17, Course Hero Intern

  • Left Quote Icon

    The ability to access any university’s resources through Course Hero proved invaluable in my case. I was behind on Tulane coursework and actually used UCLA’s materials to help me move forward and get everything together on time.

    Student Picture

    Jill Tulane University ‘16, Course Hero Intern

Stuck? We have tutors online 24/7 who can help you get unstuck.
A+ icon
Ask Expert Tutors You can ask You can ask ( soon) You can ask (will expire )
Answers in as fast as 15 minutes
A+ icon
Ask Expert Tutors