A. DIRECT COST
SPL I
-
CLEARING AND LAY-OUT
240.24
sq.m.
A. Materials
Coco or Lawaan Lumber, 40 - 2" x 2" x 12'
200.00
bd.ft
15.00
Nylon # 30
1.00
kg
330.00
CW Nails # 3
20.00
kg
70.00
Sub-Total
B. Labor
Carpenter
3.00
day
2.00
350.00
Laborers
2.00
day
2.00
300.00
Sub-Total
TOTAL FOR CLEARING AND LAY-OUT
ITEM 103
-
STRUCTURAL EXCAVATION
49.79
cu.m.
A. Labor
Laborers
5.00
days
5.00
350.00
Sub-Total
TOTAL FOR STRUCTURAL EXCAVATION
ITEM 405
-
STRUCTURAL CONCRETE
40.75
cu.m.
A. Materials
Portland Cement Type 1
368.00
bags
265.00
Screened Gravel 3/4"
60.00
cu.m.
1,000.00
Washed Sand
21.00
cu.m.
800.00
Ordinary Plywood, 4' x 8' x 1/4"
85.00
shts.
385.00
Coco or Lawaan Lumber, 100 pcs 2" x 3" x 12'
1,180.00
bd.ft.
15.00
Coco or Lawaan Lumber, 100 pcs 2" x 2" x 12'
4,768.00
bd.ft.
15.00
CW Nails # 1½"
15.00
kgs.
70.00
CW Nails # 2½"
20.00
kgs.
70.00
CW Nails # 4"
43.00
kgs.
70.00
Sub-Total
B. Labor
Carpenters
10.00
days
3.00
400.00
Masons
12.00
days
3.00
400.00
Laborers
12.00
days
6.00
350.00
#REF!
CONSTRUCTION OF ONE-STOREY RESIDENTIAL BUILDING
BILL OF QUANTITIES
ITEM DESCRIPTION
QUANTITY
UNIT
No. of
Crew/
Labor
RATE PER
DAY/
UNIT COST