ACTIVITY TIMES IMMEDIATE 3-TIME ESTIMATE PREDECESSORS Activity Node a m b μ σ Node Predecessor Measure Land A 5 8 15 B A Stake Layout B 7 12 20 C A Environmen Anal C 10 17 31 D B Foundation D 12 22 38 E C Construction Papers E 6 13 21 F C Building Framework F 11 15 27 G C Gas Line G 9 18 22 H B Electrical Wiring H 25 27 31 H E Interior Plumbing I 18 20 35 I B Wall Construction J 12 25 32 I E Insulation K 10 23 33 J D Drywall L 25 30 35 J H Roofing M 3 10 20 K F Restaurant Construc N 25 40 55 K I Swimming Pool O 9 20 40 L F Fencing P 6 10 21 L I Telephone Lines Q 12 22 40 M J Sewers R 26.44 31.73 47.6 M K Snack Bar S 10 20 30 N G Stream Building T 45 55 65 O G Outside Lighting U 8 12 15 O J Parking Lots V 3 5 7 O K Drainage W 5 10 18 O L Safety Inspection X 9 15 25 P G Landscping Y 6 24 40 P J Final Permits Z 10 15 25 P K P L Q M Q O R M R O S N T N U P U Q U S V P V Q V S W P W Q W S W T X U X W Y R Y V Z X Z Y KNOWN μ and σ
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
CRITICAL PATH ANALYSIS MEAN 186.66 STANDARD DEVIATION* 10.47
Background image of page 2
This is the end of the preview. Sign up to access the rest of the document.

Page1 / 2

Case 5.2-P-L-No - ACTIVITY TIMES 3-TIME ESTIMATE Activity...

This preview shows document pages 1 - 2. Sign up to view the full document.

View Full Document Right Arrow Icon
Ask a homework question - tutors are online