Gizem Dogan OPM 311 Section-90 ASSIGNMENT 7 5) a. Activity Time Early Late Slack (LS-ES / LF-EF) ES EF LS LF 1-2 4 0 4 7 11 7 1-3 10 0 10 0 10 0 2-4 9 4 13 12 21 8 2-5 8 4 12 11 19 7 3-6 6 10 16 10 16 0 4-7 5 13 18 21 26 8 5-8 7 12 19 19 26 7 7-10 2 18 20 26 28 8 8-10 2 19 21 26 28 7 6-9 4 16 20 16 20 0 9-11 5 20 25 20 25 0 11-12 6 25 31 25 31 0 10-12 3 21 24 28 31 7 The Critical Path Sequence is SNODE FNODE TIME 1 3 10 3 6 6 6 9 4 9 11 5 11 12 6 31 7) a. 6-8-11 5-6-9 c      5-6-7 e    a        2-3-7 5-6-7 9-12-15 g f d    5-7-8       8-8-11 i 4-4-5 b h
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
b. Path Activity Times 2 act σ 2 path σ path σ To Tm Tp e-c-a e 5 6 9 16/36 a 6 8 11 25/36 1.25 1.12 c 5 6 7 4/36 g-f-d g 2 3 7 25/36 f 5 6 7 4/36 1.8 1.34 d 9 12 15 36/36 i-h-b i 5 7 8 9/36 h 4 4 5 1/36 0.53 0.73 b 8 8 11 9/36 Path Activity Times Path  To Tm Tp 6 e-c-a e 5 6 9 6.33 a 6 8 11 8.17 20.5 c 5 6 7 6 g-f-d g 2 3 7 3.5 f 5 6 7 6 21.5 d 9 12 15 12 i-h-b i 5 7 8 6.83 h 4 4 5 4.17 19.50 b 8 8 11 8.5 b. Probability that the project can be completed in 24 days or less;
Background image of page 2
Image of page 3
This is the end of the preview. Sign up to access the rest of the document.

This note was uploaded on 01/04/2010 for the course OPM 311 taught by Professor Rui during the Spring '08 term at Binghamton University.

Page1 / 8

opm assignment 7 - GizemDogan OPM311Section90 ASSIGNMENT7...

This preview shows document pages 1 - 3. Sign up to view the full document.

View Full Document Right Arrow Icon
Ask a homework question - tutors are online