12-100hw6 - 12-100Introduction to Civil and Environmental Engineering Spring 2008 Homework 6 Due 5 March 2008 1.Consider the following activities

Info iconThis preview shows pages 1–3. Sign up to view the full content.

View Full Document Right Arrow Icon

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
This is the end of the preview. Sign up to access the rest of the document.

Unformatted text preview: 12-100Introduction to Civil and Environmental Engineering Spring 2008 Homework 6. Due: 5 March 2008 1.Consider the following activities in a project: Activity Predecessors Duration (days) A - 4 B A 8 C A 10 D - 6 E B 2 F B,D 4 G C,D 5 H A,D 6 I H 8 J E,F 3 K E,I 9 L F 10 M G,J,K 5 N G,I 2 O L,N 6 a)Draw a Gantt chart showing the earliest start and earliest finish dates of these activities. What is the total number of days needed to complete this project? Determine the sequence of activities (the critical path) that establishes the total duration of this project. b)Determine the total project duration, and critical path, if activity K takes 12 days instead of 9. c)Determine the total project duration, and critical path, if activity K takes 2 days instead of 9. 2. A construction project has 14 activities, A through N, with predecessors, durations, and manpower requirements as listed in the table below. Draw a Gantt chart for the project. What is the minimum overall project duration? Which activities constitute the critical path? If every activity is started at its earliest possible date, what are the maximum and minimum daily manpower requirements? Activity Predecessors Duration, days Manpower A - 4 3 B A 3 3 C - 5 3 D - 3 3 E A 2 3 F A 6 3 G A 5 3 H B, C 4 3 I B, C 5 3 J D 4 3 K E 3 3 L E 4 3 M F, H, K 4 3 N G, I, J 4 3 3. 3....
View Full Document

This note was uploaded on 01/25/2010 for the course CE 12100 taught by Professor Irvin during the Spring '08 term at Carnegie Mellon.

Page1 / 3

12-100hw6 - 12-100Introduction to Civil and Environmental Engineering Spring 2008 Homework 6 Due 5 March 2008 1.Consider the following activities

This preview shows document pages 1 - 3. Sign up to view the full document.

View Full Document Right Arrow Icon
Ask a homework question - tutors are online