6 14 Activity O M P t(e) sigma^2(e) C 8 A 1 3 4 2.833 0.250 0 3 3 6 6 14 14 17 17 22 B 2 3 4 3.000 0.111 A 3 B 3 E 3 F 5 C 5 8 10 7.833 0.694 0 3 3 6 6 11 14 17 17 22 D 4 5 6 5.000 0.111 D 5 E 2 3 5 3.167 0.250 9 14 F 3 5 6 4.833 0.250 Total Days on Critical Path = 21.667 Total variance on Critical Path=