Christopher Neff ENSC 481 CHPT 5 HMWK 3. Top down estimates usually are derived from someone who uses experience and/or information to determine the project duration and total cost. The bottom-up approach uses several people with relevant experience with the task can improve the time and cost estimate. 3. Element LOW
Background image of page 1
This is the end of the preview. Sign up to access the rest of the document.

Unformatted text preview: Average HIGH TOTAL # inputs 10 20 # outputs 20 120 # inquires 10 40 # files 30 360 # interfaces 50 750 TOTAL 1290 a. The estimated project duration is 43 months. b. If 20 people are available the project will take 12.9 months. c. For the project to be finished in 6 months 43 people must be working on it....