pg 612 First Come First Serve slack CR PT DD completion time lateness A 6 7 6 0 1 1.17 B 3 4 9 5 1 1.33 C 3 3 12 9 0 1 D 8 5 20 15 -3 0.63 47 29 Average Completion 11.75 Average Late 7.25 Max Late FCFS **using the minimum slack rule in this occurrence just happens t EDD SPT CR Critical Ratio Min Slack
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Shortest Processing Time PT DD completion time lateness PT C 3 3 3 0 C 3 B 3 4 6 2 B 3
Background image of page 2
Background image of page 3
This is the end of the preview. Sign up to access the rest of the document.

Unformatted text preview: A 6 7 12 5 D 8 D 8 5 20 15 A 6 41 22 Average Completion 10.25 Average Completion Average Late 5.5 Average Late Max Late Max Late to use the same rule as FCFS Earliest Due Date DD completion time lateness 3 3 4 6 2 5 14 11 7 20 13 43 26 10.75 6.5 13...
View Full Document

This note was uploaded on 05/22/2010 for the course SCI 123 taught by Professor Smith during the Spring '10 term at Kirkwood Community College.

Page1 / 3

Sequencing Jobs-feb10 - A 6 7 12 5 D 8 D 8 5 20 15 A 6 41...

This preview shows document pages 1 - 3. Sign up to view the full document.

View Full Document Right Arrow Icon
Ask a homework question - tutors are online