2
2 days
7
4 days
1 day
2 days
6
4 days
1 day
2 days
5 days
4
2 days
5
Assume that the dead line for the project is 18 days. Solve the network. That
is, calculate the ES, EF, LS, LF and the slack “s” for each activity. Identify the
critical path.
1
3 days
8
3
This
preview
has intentionally blurred sections.
Sign up to view the full version.
2
2 days
7
4 days
ES:4
EF:4
LS:14 LF: 14
s
: 10
2 days
6
4 days
1 day
2 days
ES:7
EF:8
5 days
LS:13 LF:14
s: 6
*
4
2 days
5
The critical activities are; (1