PMP_Patel_NumericProblemsChapter9

PMP_Patel_NumericProblemsChapter9 - Normal Network diagram...

Info iconThis preview shows page 1. Sign up to view the full content.

View Full Document Right Arrow Icon
This is the end of the preview. Sign up to access the rest of the document.

Unformatted text preview: Normal Network diagram for problem 9 - page 425 4 C1 10 0 A4 D5 0 0 Start 0 0 3 E4 0 B3 2 5 3 F1 6 7 4 3 5 9 7 7 4 0 4 4 9 9 4 4 9 9 11 11 5 5 Suppose A and D are both reduce by one day at cost of 15$/day of reduction 3 C1 8 0 A3 0 0 Start 0 0 3 3 E4 3 0 B3 0 3 3 0 3 3 D4 3 4 9 4 I2 9 7 7 7 7 7 7 4 H5 5 3 F1 4 4 5 Suppose A and D are both reduce by two day each at cost of 15$/day of reduction 2 C1 8 0 A2 2 0 Start 0 0 4 3 E4 3 0 B3 0 3 5 3 F1 4 5 4 3 4 H5 7 0 4 2 D3 7 7 7 5 7 2 9 9 3 I2 3 Suppose D is reduce by three day at cost of 15$/day of reduction 4 C1 8 0 A4 5 0 Start 0 0 6 3 E4 3 0 B3 0 3 5 3 F1 4 5 4 3 4 H5 7 0 6 4 D1 7 7 7 5 7 4 9 9 5 I2 5 Suppose A and D are reduced to 1 day each at cost of $ 15/ reduction day 1 C1 8 0 A1 5 0 Start 0 0 6 3 E4 3 0 B3 0 3 5 3 F1 4 5 4 3 4 H5 7 0 6 1 D1 7 7 7 2 7 1 9 9 2 I2 2 Activities E ,G and H are reduced by one day at cost of 25 $/day 4 C1 9 0 A4 0 4 4 D5 0 Start 0 0 0 4 9 9 9 9 4 10 10 5 5 0 B3 3 3 6 3 E3 6 6 9 4 7 3 F1 4 6 7 From above all network diagrams and the related solution outcome, the least cost approach to crash the project 2 da at cost of $ 30, which results into project duration of 11 days. The sh paths i)Start -A-D-G-J-End ii)Start - B-E-G-J-End . The cost of 7 I2 13 13 End 12 13 G3 12 12 J1 9 12 H5 12 13 13 13 13 This is normal time cost diagram of the project.Clearly, we can see that Critical Path of the project is Start-AD-G-J-End. Also, the project shall be completed in 13 days. 6 11 11 End 10 G3 10 10 J1 10 9 10 11 11 11 11 When the activity A and D are reduced by 1 day each, the project has two critical paths i)Start -A-D-G-J-End ii)Start - B-E-G-J-End The cost of crashing the project is $30 for both the activities 11 5 11 11 End 10 G3 10 10 J1 10 9 10 11 11 11 11 11 When the activity A and D are reduced by 2 day each, the project has same critical path Start -A-D-G-J-End The cost of crashing the project is $60 for both the activities.The Project duration is 11 days. 7 11 11 End 10 G3 10 10 J1 10 9 10 11 11 11 11 When the activity D id reduced by 3 day , the project has same critical path -Start A-D-G-J-End The cost of crashing the project is $45 for crashing D.The Project duration is 11 days. 11 4 11 11 End 10 G3 10 10 J1 10 9 10 11 11 When the activity A and D are reducedto 1 day , the project has same critical path -Start -A-D-G-J-End The cost of crashing the project is ($45 + $60) = $ 105 for crashing activities A and D.The Project duration is 11 days. 11 11 11 7 I2 12 12 End 11 G2 11 12 12 12 11 J1 11 12 12 When the activities E, G, H are reducedto 1 day , the project has same critical path -Start -A-D-G-J-End The cost of crashing the project is $75 for crashing activities A and D.The Project duration is 12 days. 8 H4 11 -Start -A-D-G-J-End The cost of crashing the project is $75 for crashing activities A and D.The Project duration is 12 days. proach to crash the project 2 days is : crashing activities A and D by one day each The shortest Crash duration is 11 days , with two critical The cost of Crashing in $ 30. normal time cost f the project.Clearly, e that Critical Path of t is Start-Ad. Also, the project ompleted in 13 days. , G, H are reducedto s same critical path -D-G-J-End the project is $75 for A and D.The Project 2 days. Activity A D E G H Crash Time(days) 1 1 3 2 4 Crash Cost($) 1*15=15 1*15=15 1*25=25 1*25=25 1*25=25 Normal Time(days) 4 5 4 3 5 Normal Cost($) 0 0 0 0 0 Normal Cost($) 0 0 0 0 0 ...
View Full Document

This note was uploaded on 11/08/2010 for the course MBA PMP 575 taught by Professor Drack during the Spring '10 term at RMU.

Ask a homework question - tutors are online