PMP575_patel_NumericProblemsChapter8

PMP575_patel_NumericProblemsChapter8 - 8 D7 10 0 A8 0 0...

Info iconThis preview shows pages 1–4. Sign up to view the full content.

View Full Document Right Arrow Icon
8 15 rectangle represents D7 17 0 A8 8 0 Start 8 11 11 17 C3 E6 0 0 8 17 0 18 B10 F7 1 11 12 19 8a) The critical path of the project is Start A-C-E-G End 8b) It will take 22 days to complete the entire project 8c) Yes, the Activity B can be delayed without delaying complete project by 1 (one) day
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
activities arrows shows precedence relati 17 22 G5 17 22 End 22 22 18 21 H3 19 22
Background image of page 2
0 5 5 10 A5 E5 6 11 16 3 6 12 B3 F6 0 Start 0 0 G10 0 C6 I4 0 0 D7 H8
Background image of page 3

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Background image of page 4
This is the end of the preview. Sign up to access the rest of the document.

This note was uploaded on 11/08/2010 for the course MBA PMP 575 taught by Professor Drack during the Spring '10 term at RMU.

Page1 / 4

PMP575_patel_NumericProblemsChapter8 - 8 D7 10 0 A8 0 0...

This preview shows document pages 1 - 4. Sign up to view the full document.

View Full Document Right Arrow Icon
Ask a homework question - tutors are online