Sharon Construction Corporation Nirali Patel John Wenc Daniel Sosa William Haselberger
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Question no.1 Analyze the five proposals and make recommendations based on expected cost.
Background image of page 2
About the Company: Sharon Construction Company is awarded the contract of 20,000 seat stadium Construction must start by February 15 and completed within one year Contract states the penalty of $ 15000 per week of delay beyond February 15 of next year
Background image of page 3

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Some Aspects to be taken into Consideration: Labor agreements expires on Nov 30 Past Experiences indicates 50-50 chances of the strike Perspective length of the strike reveals that – - 70% chances that strike last 8 weeks - 30% chances that strike last 12 weeks Colder December might be expected, which was not consider during earlier estimation, - If so concrete pouring will cause cost of 500$/week for heating In case of any delay, Overhead expense of $500/ week would be incurred
Background image of page 4
Scenarios that could happen based on given Case: 1)There will be no Strike and no colder December 2)The weather is cold in December and no Strike 3)The Strike occurs and no cold December with two sub-scenario - a) 70% chance strike last 8 weeks b) 30 % chance strike last 12 weeks 4) Both strike (obviously with two sub scenarios) occurs and weather is colder in December
Background image of page 5

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Critical Path according to Appendix:
Background image of page 6
Proposal 1: Expedite the pouring of the seat gallery supports. This would cost $20,000 and cut the duration of the activity to six weeks.
Background image of page 7

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Pros of following Proposal 1: The Critical Path does not change. The project would complete 6 weeks ahead of schedule. Other tasks can be done in parallel. When the task is complete the project will be completed. It will buy you 6 weeks for any other unexpected delays. (Penalty is $15,000 per week if project is delayed)
Background image of page 8
Critical Path for proposal 1:
Background image of page 9

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Cons of following Proposal 1: If December is cold as predicted you will be spending the $20,000 for crashing and you will be also adding additional cost for special equipment. If the union goes on strike, the $20,000
Background image of page 10
Image of page 11
This is the end of the preview. Sign up to access the rest of the document.

This note was uploaded on 11/08/2010 for the course MBA PMP 575 taught by Professor Drack during the Spring '10 term at RMU.

Page1 / 28

PMP575_Team1_Case_sharonConstructionCompany_Final - Sharon...

This preview shows document pages 1 - 11. Sign up to view the full document.

View Full Document Right Arrow Icon
Ask a homework question - tutors are online