More on Capacity Management BUAD311 Operations Management Session 4 1
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
2 More on Capacity Management So far, we analyzed the process given the capacity. How much capacity do we need to meet the demand?
Background image of page 2
3 Capacity Requirement: Example Kristen saw a high demand and would like to produce 26 dozen cookie (in one dozen order) a night. How many ovens and mixers does Kristen need? What are the utilization rates of Kristen and her roommate?
Background image of page 3

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
4 Capacity Requirement Total Throughput Rate = 26 dozen/night = 6.5 dozen/hour Capacity of an oven = 24 dozen/night =6 dozen/hour Capacity of a mixer = 40 dozen/night =10 dozen/hour Two ovens and one mixer
Background image of page 4
Capacity Requirement Utilization rate of Kristen 26/(240/8) = 86.7% Utilization rate of Roommate 26/(240/4) = 43.3% What if Kristen would like to produce 36 dozen cookie (in one dozen order) a night? Is this possible? Note Kristen’s capacity is…. Yes, by
Background image of page 5

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Image of page 6
This is the end of the preview. Sign up to access the rest of the document.

This note was uploaded on 02/15/2011 for the course BUAD 311 at USC.

Page1 / 17

311_session_4_more_on_capacity - More on Capacity...

This preview shows document pages 1 - 6. Sign up to view the full document.

View Full Document Right Arrow Icon
Ask a homework question - tutors are online