Module 4 Exam Here is your test result.The dots represent the choices you have made. The highlighted questions are the questions you have missed. Remediation Accessed shows whether you accessed those links.'N' represents links not visited and 'Y' represents visited links. Back to Status page contains 21 Questions 1) How does the Integrated Master Schedule (IMS) relate to the Integrated Master Plan (IMP)? [4.2.1 - Relate the relationship of the Integrated Master Plan (IMP) to the Integrated Master Schedule (IMS).] 2) In which step of the Schedule Development and Management Process do you describe all the tasks and activities that must be completed to achieve program objectives? [4.3.1 - Select the six steps for the schedule development and management process.]Identify Tasks Sequence Tasks Construct Schedules Determine Resource Requirements 3) Which task dependency involves the successor not being able to finish until the predecessor finishes? [4.3.2 -Given a task relationship scenario, identify the standard type of dependencies or relationships between schedule activities.] [Remediation Accessed :N] Finish-to-Finish (FF) Finish-to-Start (FS) Start-to-Start (SS) Start-to-Finish (SF) Page 1 of 6 DAU 6/12/2018
4) After starting the Schedule Development and Management Process by identifying a comprehensive list of program tasks, assigning identifiers, and including additional information such as potential constraints, what sort of product should the program manager (PM) expect to have? [4.3.3 - Identify the end result of the identification of schedule tasks step.]

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture