JKY@EMGT@UHCL Information Technology Project Management, Sixth Edition Defining activities : identifying the specific activities that the project team members and stakeholders must perform to produce the project deliverables Sequencing activities : identifying and documenting the relationships between project activities Estimating activity resources : estimating how many resources a project team should use to perform project activities Estimating activity durations : estimating the number of work periods that are needed to complete individual activities Developing the schedule : analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule Controlling the schedule : controlling and managing changes to the project schedule 2
Background image of page 2
JKY@EMGT@UHCL Information Technology Project Management, Sixth Edition 3
Background image of page 3

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
JKY@EMGT@UHCL Information Technology Project Management, Sixth Edition 4
Background image of page 4
JKY@EMGT@UHCL Information Technology Project Management, Sixth Edition An activity or task is an element of work normally found on the work breakdown structure (WBS) that has an expected duration, a cost, and resource requirements 5
Background image of page 5

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
JKY@EMGT@UHCL Information Technology Project Management, Sixth Edition 6
Background image of page 6
JKY@EMGT@UHCL Information Technology Project Management, Sixth Edition 7
Background image of page 7

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
JKY@EMGT@UHCL Information Technology Project Management, Sixth Edition 8
Background image of page 8
JKY@EMGT@UHCL Information Technology Project Management, Sixth Edition 9
Background image of page 9

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
JKY@EMGT@UHCL Information Technology Project Management, Sixth Edition A milestone is a significant event that normally has no duration It often takes several activities and a lot of work to complete a milestone They’re useful tools for setting schedule goals and monitoring progress Examples include obtaining customer sign-off on key documents or completion of specific products 10
Background image of page 10
JKY@EMGT@UHCL Information Technology Project Management, Sixth Edition Involves reviewing activities and determining dependencies A dependency or relationship is the sequencing of project activities or tasks You must determine dependencies in order to use critical path analysis 11
Background image of page 11

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
JKY@EMGT@UHCL Information Technology Project Management, Sixth Edition 12
Background image of page 12
JKY@EMGT@UHCL Information Technology Project Management, Sixth Edition 13
Background image of page 13

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
JKY@EMGT@UHCL Information Technology Project Management, Sixth Edition Activities are represented by boxes Arrows show relationships
Background image of page 14
Image of page 15
This is the end of the preview. Sign up to access the rest of the document.

This note was uploaded on 02/28/2011 for the course EGMT 5330 taught by Professor Jeong during the Spring '11 term at UH Clear Lake.

Page1 / 48

PPM_CH6 - Information Technology Project Management, Sixth...

This preview shows document pages 1 - 15. Sign up to view the full document.

View Full Document Right Arrow Icon
Ask a homework question - tutors are online