F 3 A 3 D 4 G 6 B 1 H 4 E 5 C 2 Bill Frino MNMK 413P March 21, 2011 Chapter 9 Problem #7 Embassy Club Condominium Project Network A. The critical activities are: A-D-E-H. B. Activity F has the most slack time with 4.
Background image of page 1
This is the end of the preview. Sign up to access the rest of the document.

Unformatted text preview: C. Yes, the project would be complete within 16 weeks while the maximum time allotted is 17 weeks....