OM 335 Bagchi Names: SOLUTION Group Homework-4 The capacity of the Refrigerated Stage must be increased due to the shift in mix. The project plan for this project is as follows: Activity Description Predecessor a m b Mean Variance A Raise Funds - 10 days 11 days 12 days 11 0.111 B Financial Evaluation A 20 24 34 25 5.444 C Engineering Design A 12 15 24 16 4.000 D Facilities Design C 5 6 7 6 0.111 E Install New Pick System B, D 30 35 46 36 7.111 F Small Scale Test E 14 16 24 17 2.778 G Large Scale Test F 35 50 77 52 49.000 H Document Procedures E 66 69 72 69 1.000 I Train Employees E 62 62 62 62 0 J Ramp-Up to Volume G, H, I 10 12 14 12 0.444 1. Supply the missing entries in the Table above; draw the project network diagram; for each path calculate the mean and standard deviation of the path time; calculate the expected project duration and identify the critical activities. Path Mean Variance Std. Dev. A-B-E-I-J 146 13.11 3.621 A-B-E-H-J 153 14.11 3.756 A-B-E-F-G-J 153 64.888 8.055 A-C-D-E-I-J 143 11.777 3.432 A-C-D-E-H-J 150 12.777 3.574 A-C-D-E-F-G-J 150 63.555 7.972 The expected project duration is 153 days and the critical activities are activities on the two critical paths (in bold) in the diagram above – A, B, E, F, G, H and J . 1 A,1 1 B,2 5 C,1 6 D,6 E,3 6 F,1 7 H,6 9 I,62 G,52 J,1 2
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
2. Complete the Table below by using the mean activity time of each activity as the estimate of that activity’s duration. Label
Background image of page 2
Image of page 3
This is the end of the preview. Sign up to access the rest of the document.

This note was uploaded on 04/20/2011 for the course OM 335 taught by Professor Jonnalagedda during the Spring '08 term at University of Texas.

Page1 / 4

GS-4 - OM 335 Bagchi Group Homework-4 Names SOLUTION The...

This preview shows document pages 1 - 3. Sign up to view the full document.

View Full Document Right Arrow Icon
Ask a homework question - tutors are online