Janice Thomas 1/10/11 10:02 AM Quiz2 Completed 95 out of 100 points 25 minutes, and 32 seconds out of 1 hour. The quiz consists of 20 equally-weighted, objective-type questi larger pool of questions. The quiz may be taken "open book". It
Image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full Document Right Arrow Icon
Question 1 5 out of 5 points A contractor's project being analyzed by PERT has an estimated time for the critical path of 120 days. The sum of all activity variances is 81; the sum of variances along the critical path is 64. The probability that the project will take 130 or more days to complete is Answer Selected Answer: 0.1057 Question 2 5 out of 5 points Ethical issues that may arise in projects large and small include Answer Selected Answer: all of these
Image of page 2
Question 3 5 out of 5 points Which of the following statements regarding PERT times is true? Answer Selected Answer: The probable time estimate is calculated as t = (a + 4m + b)/6. Question 4 5 out of 5 points A network has been crashed to the point where all activities are critical. Additional crashing Answer Selected Answer: may require crashing multiple tasks simultaneously
Image of page 3

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full Document Right Arrow Icon
Image of page 4
This is the end of the preview. Sign up to access the rest of the document.

{[ snackBarMessage ]}

What students are saying

  • Left Quote Icon

    As a current student on this bumpy collegiate pathway, I stumbled upon Course Hero, where I can find study resources for nearly all my courses, get online help from tutors 24/7, and even share my old projects, papers, and lecture notes with other students.

    Student Picture

    Kiran Temple University Fox School of Business ‘17, Course Hero Intern

  • Left Quote Icon

    I cannot even describe how much Course Hero helped me this summer. It’s truly become something I can always rely on and help me. In the end, I was not only able to survive summer classes, but I was able to thrive thanks to Course Hero.

    Student Picture

    Dana University of Pennsylvania ‘17, Course Hero Intern

  • Left Quote Icon

    The ability to access any university’s resources through Course Hero proved invaluable in my case. I was behind on Tulane coursework and actually used UCLA’s materials to help me move forward and get everything together on time.

    Student Picture

    Jill Tulane University ‘16, Course Hero Intern