Homework 2 BUSQOM 1070, Spring 2011 Assigned: Monday, January 24, 2011 Due: Monday, January 31, 2011 From Chapter 3 (pages 90 – 94) in Heizer/Render 10 th Edition: Problem 3.3 Critical path is A–C–F–H. Time = 21 days. This is an AON network. Problem 3.10 Note: Activity times are shown as an aid for Problem 3.11. They are not required in the solution to 3.10. Problem 3.11 Activity Time ES EF LS LF Slack Critical A 6 0 6 2 8 2 No B 7 0 7 0 7 0 Yes C 3 6 9 8 11 2 No D 2 6 8 12 14 6 No E 4 7 11 7 11 0 Yes F 6 7 13 8 14 1 No G 10 11 21 11 21 0 Yes H 7 13 20 14 21 1 No The critical path is given for activities B, E, G. Total project completion time is 21 days.