Chapter 4: Comparison Methods Part 1 Present Worth, Annual Worth, Payback Period Levelized Cost Assumptions (for now): Costs and benefits are measurable in $ Sufficient funding is available No uncertainty No tax (Chapter 8) No inflation or deflation (Chapter 9)
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Relations Among Projects Independent: Costs and benefits of one project do not depend on whether the other is chosen – e.g., a marketing ad campaign project and office equipment decision Mutually Exclusive (ME): One project is excluded if the other is chosen – e.g., one-storey versus two-storey building on one village lot Related, but not mutually exclusive: Costs and benefits of one project depend on whether or not the other is chosen – e.g., city can spend up to $30 million on: (a) pool @$10 million; (b) rink @$15 million; (c) community hall @$12 million
Background image of page 2
Example 4-1: The AAM Company is considering opening three new marble quarries, call them T, L and M. A cutter-loader machine may be purchased, but only if quarry L goes ahead. The overall budget is limited to $2.5 million. Thus the projects are related. What feasible, mutually exclusive alternatives are available ? Project First Cost T quarry $0.9 million L quarry $1.4 million M quarry $1.0 million cutter-loader $0.4 million (only with quarry L)
Background image of page 3

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
# T? L? M? Option Cost 1 No No No 2 No No Yes 3 No Yes No 4 No Yes Yes 5 Yes No No 6 Yes No Yes 7 Yes Yes No 8 Yes Yes Yes Generate T, L, M combinations:
Background image of page 4
# T? L? M? Option Cost 1 No No No no quarry 0 2 No No Yes M 1.0 M 3 No Yes No L 1.4 M 4 No Yes Yes LM 2.4 M 5 Yes No No T 0.9 M 6 Yes No Yes TM 1.9 M 7 Yes Yes No TL 2.3 M 8 Yes Yes Yes TLM 3.3 M Generate T, L, M combinations; note total first cost:
Background image of page 5

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Include Cutter-Loader (symbol C) only relevant for quarry L # T? L? M? C? Option Cost 1 No No No No no quarry 0 2 No No Yes No M 1.0 M 3 No Yes No No L 1.4 M 4 No Yes No Yes 5 No Yes Yes No LM 2.4 M 6 No Yes Yes Yes 7 Yes No No No T 0.9 M 8 Yes No Yes No TM 1.9 M 9 Yes Yes No No TL 2.3 M 10 Yes Yes No Yes 11 Yes Yes Yes No TLM 3.3 M 12 Yes Yes Yes Yes
Background image of page 6
# T? L? M? C? Option Cost 1 No No No No do nothing 0 2 No No Yes No M 1.0 M 3 No Yes No No L 1.4 M 4 No Yes No Yes LC 1.8 M 5 No Yes Yes No LM 2.4 M 6 No Yes Yes Yes LMC 2.8 M 7 Yes No No No T 0.9 M 8 Yes No Yes No TM 1.9 M 9 Yes Yes No No TL 2.3 M 10 Yes Yes No Yes TLC 2.7 M 11 Yes Yes Yes No TLM 3.3 M 12 Yes Yes Yes Yes TLMC 3.7 M Include Cutter-Loader (symbol C) only relevant for quarry L
Background image of page 7

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
# T? L? M? C? Option Cost 1 No No No No do nothing 0 2 No No Yes No M 1.0 M 3 No Yes No No L 1.4 M 4 No Yes No Yes LC 1.8 M 5 No Yes Yes No LM 2.4 M 6 No Yes Yes Yes LMC 2.8 M 7 Yes No No No T 0.9 M 8 Yes No Yes No TM 1.9 M 9 Yes Yes No No TL 2.3 M 10 Yes Yes No Yes TLC 2.7 M 11 Yes Yes Yes No TLM 3.3 M 12 Yes Yes Yes Yes TLMC 3.7 M Eliminate options that exceed $2.5 million Answer: no new quarry, M, L, LC, LM, T, TM, TL are feasible
Background image of page 8
Proposal Present Worth ($) Space Required (square metres) A 120,000 600 B 52,000
Background image of page 9

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Image of page 10
This is the end of the preview. Sign up to access the rest of the document.

Page1 / 41

Ch4 - Chapter 4: Comparison Methods Part 1 Present Worth,...

This preview shows document pages 1 - 10. Sign up to view the full document.

View Full Document Right Arrow Icon
Ask a homework question - tutors are online