Chapter 9 Problem 2: Utilization Effective = apacity EffectiveC ut ActualOutp (100%) = 700 950 (100%) = 135.7% Utilization Design = city DesignCapa ut ActualOutp (100%) = 1000 950 (100%) = 95% The utilization rates show that the facility’s current output is slightly below its design capacity and considerably higher than its effective capacity. The facility can probably operate at the effective level for only a short time. Problem 4: Effective capacity = 35 customers/day Design capacity = 80 customers/day Problem 6: Utilization Effective = apacity EffectiveC ut ActualOutp (100%) = 260 250 (100%) = 96.2% Utilization Design = city DesignCapa ut ActualOutp (100%) = 300 250 (100%) = 83.3% The utilization rates show that the facility’s current output is below its design and effective capacities. Problem 8: a. Low Demand (0.30) $50,000 Large High Demand (0.70) $80,000 Low Demand (0.30) $40,000 Small Expand $50,000 High Demand (0.70)
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
b. EV small expansion = 50,000(0.70) + 40,000(0.30) = $47,000
Background image of page 2
Image of page 3
This is the end of the preview. Sign up to access the rest of the document.

This note was uploaded on 06/12/2011 for the course MNGT 368 taught by Professor Curthurds during the Spring '08 term at Nicholls State.

Page1 / 3

ch09 - Chapter 9 Problem 2: ActualOutput 950 (100%) =...

This preview shows document pages 1 - 3. Sign up to view the full document.

View Full Document Right Arrow Icon
Ask a homework question - tutors are online