13-3 - = .92 On day 51 the project is $50 over budget and...

Info iconThis preview shows page 1. Sign up to view the full content.

View Full Document Right Arrow Icon
CIS 550 / Week 11 13-E2 EV = $600 AC = $650 PV = $560 CV = EV – AC = $600 – $650 = -$50 SV = EV – PV = $600 – $560 = $40 CPI = EV / AC = $600 / $650
Background image of page 1
This is the end of the preview. Sign up to access the rest of the document.

Unformatted text preview: = .92 On day 51 the project is $50 over budget and ahead of schedule. $.92 worth of work is being completed for every dollar spent....