Chapter 03 - Project Management
CHAPTER 3
PROJECT MANAGEMENT
Review and Discussion Questions
1.
What was the most complex project that you have been involved in?
Give examples of the
following as they pertain to the project: the work breakdown structure, tasks, subtasks, and
work package.
Were you on the critical path?
Did it have a good project manager?
Obviously, the answer will vary.
Remember that the project could be in a non-profit environment
as well.
School plays, fund-raisers, and social events could all be examples of projects.
2.
What are some reasons project scheduling is not done well?
Several problems with project scheduling are discussed at the end of the chapter.
The
uncertainties inherent in the activities comprising the network of any project make it necessary to
update the schedule on a regular basis.
Maintaining accurate time and cost estimates is often
difficult and frustrating.
Managing this evolving process requires a discipline that is not always
available.
3.
Discuss the graphic presentations in Exhibit 3.4.
Are there any other graphic outputs you
would like to see if you were project manager?
The various graphs and charts presented are typical of the graphical techniques for presenting the
necessary data.
Most are adaptable to computer programming.
The major requirements in the
graphics package include planned activities related to time, a milestone chart to show major
achievements, a breakdown to show how funds were spent plus a plot of actual completion versus
planned.
4.
Which characteristics must a project have for critical path scheduling to be applicable?
What
types of projects have been subjected to critical path analysis?
Project characteristics necessary for critical path scheduling to be applicable are:
a.
Well-defined jobs whose completion marks the end of the project.
b.
The jobs of tasks are independent in that they may be started, stopped, and conducted
separately within a given sequence.
c.
The jobs or tasks are ordered in that they must follow each other in a given sequence.
d.
An activity once started is allowed to continue without interruption until it is
completed.
A wide variety of projects have used critical path analysis.
Some industries that more commonly
use this approach include aerospace, construction, and computer software.
22
This
preview
has intentionally blurred sections.
Sign up to view the full version.
Chapter 03 - Project Management
5.
What are the underlying assumptions of minimum-cost scheduling?
Are they equally
realistic?
The underlying assumptions of minimum cost scheduling are that it costs money to expedite a
project activity and it costs money to sustain or lengthen the completion time of the project.
While both assumptions are generally realistic, it often happens that there are little or no out-of-
pocket costs associated with sustaining a project.
Personnel are often shifted between projects,
and in the short run there may be no incentive to compete a project in “normal time.”
6.
“Project control should always focus on the critical path.”
Comment.

This is the end of the preview.
Sign up
to
access the rest of the document.
- Spring '11
- none
- Management, Project Management, Critical path, Critical path method
-
Click to edit the document details