Virginia Project FEL 1 Calculations

Virginia Project FEL 1 Calculations - 1998 Shoe Press...

Info iconThis preview shows pages 1–9. Sign up to view the full content.

View Full Document Right Arrow Icon
1998 1999 2000 0.20% 1.40% 1.20% Escalation Factor on Equipment 1.00 1.01 1.03 Shoe Press Drives and Pumps OCC Upgrade
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full Document Right Arrow Icon
2001 2002 2003 2004 2005 -0.10% 0.50% 1.50% 8.30% 6.10% 1.03 1.03 1.05 1.13 1.2 $6,000,000 $4,000,000 $1,500,000
Background image of page 2
2006 2007 2008 2009 6.70% 2.20% 5.00% 5.00% 1.28 1.31 1.38 1.44 $6,402,000 $6,542,844 $6,869,986 $7,213,486 $4,268,000 $4,361,896 $4,579,991 $4,808,990 $1,600,500 $1,635,711 $1,717,497 $1,803,371
Background image of page 3

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full Document Right Arrow Icon
Low Mid Direct Cost - Purchased Equipment 15% 27% - Purchased Equipment Erection 2% 5% - Instrumentation and Controls 3% 6% - Piping 2% 6% - Electrical Systems 2% 6% - Buildings 0% 6% - Yard Improvements 0% 2% Foundations 6% 11% - Land 0% 1% Sub-Total Direct Cost 30% 70% Indirect Cost - Engineering 3% 7% - Construction Expenses 3% 6% - Legal Expenses 0% 1% - Contractor Fee 2% 4% - Inflation 3% 6% - Contingency 3% 7% Sub-Total Indirect Cost 14% 31% Total Installed Cost 44% 100%
Background image of page 4
Factored Equipment Estimate High Low Mid High 39% 1.00 1.00 1.00 8% 0.13 0.19 0.30 8% 0.11 0.20 0.30 10% 0.07 0.22 0.37 10% 0.07 0.22 0.37 12% 0.00 0.22 0.44 4% 0.00 0.07 0.15 16% 0.22 0.41 0.59 2% 0.00 0.04 0.07 109% 1.61 2.57 3.59 8% 0.20 0.26 0.30 9% 0.20 0.22 0.33 2% 0.00 0.04 0.07 6% 0.13 0.15 0.22 8% 0.20 0.22 0.30 10% 0.20 0.24 0.37 43% 0.93 1.13 1.59 152% 2.55 3.70 5.19
Background image of page 5

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full Document Right Arrow Icon
Shoe Press 2005 Quote was for same tonnage on PM1 so not scale factor required Direct Cost Reference - Purchased Equipment Vendor equipment quote - Purchased Equipment Erection Erection Intensive - Instrumentation and Controls Controls Intensive - Piping Low - Electrical Systems Medium Intensity - Buildings None - Yard Improvements None Foundations Foundation Intensive - Land None Sub-Total Direct Cost Indirect Cost - Engineering Engineering Intensive - Construction Expenses Construction Intensive - Legal Expenses Medium Contracting Intensity - Contractor Fee High Contractor Fee Intensity - Inflation High Inflation* - Contingency Low Contingency Sub-Total Indirect Cost Total Installed Cost * Inflation incurred from the time the e
Background image of page 6
Factored Equipment Estimate Cost Estimate Low Mid High $7,213,486 1.00 1.00 1.00 $2,137,329 0.13 0.19 0.30 $2,137,329 0.11 0.20 0.30 $534,332 0.07 0.22 0.37 $1,602,997 0.07 0.22 0.37 $0 0.00 0.22 0.44 $0 0.00 0.07 0.15 $4,274,658 0.22 0.41 0.59 $0 0.00 0.04 0.07 $17,900,131 1.61 2.57 3.59 $2,137,329 0.20 0.26 0.30 $2,404,495 0.20 0.22 0.33 $267,166 0.00 0.04 0.07 $1,602,997 0.13 0.15 0.22 $2,137,329 0.20 0.22 0.30 $1,442,697 0.20 0.24 0.37 $9,992,013 0.93 1.13 1.59 $27,892,144 2.55 3.70 5.19 3.87 estimate is prepared until installed
Background image of page 7

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full Document Right Arrow Icon
2005 Quote was for same tonnage on PM1 so not scale factor required Direct Cost Reference - Purchased Equipment Vendor equipment quote - Purchased Equipment Erection Low Erection - Instrumentation and Controls Low Erection - Piping High Intensity - Electrical Systems High Intensity - Buildings None - Yard Improvements None Foundations Medium Intensity - Land None Sub-Total Direct Cost Indirect Cost - Engineering Engineering Intensive
Background image of page 8
Image of page 9
This is the end of the preview. Sign up to access the rest of the document.

{[ snackBarMessage ]}

Page1 / 225

Virginia Project FEL 1 Calculations - 1998 Shoe Press...

This preview shows document pages 1 - 9. Sign up to view the full document.