Homework Help (WK2)

Homework Help (WK2) - = 1 + 4 + 2 + 5 + 3 = ( Critical Path...

Info iconThis preview shows page 1. Sign up to view the full content.

View Full Document Right Arrow Icon
Week 2 Help CH3, Pg 82, Problem 3 Schedule the following activities using CPM: Activity Immediate Predecessor Time (Weeks) A - 1 B A 4 C A 3 D B 2 E C, D 5 F D 2 G F 2 H E, G 3 A. Draw the network. B. What is the critical path? Path Path Duration A + B + D + F + G = 1 + 4 + 2 + 2 + 2 + 3 = A + B + D + E + H
Background image of page 1
This is the end of the preview. Sign up to access the rest of the document.

Unformatted text preview: = 1 + 4 + 2 + 5 + 3 = ( Critical Path ) A + C + E + H = 1 + 3 + 5 + 3 = Note: A project cannot finish in less time than its longest path. C. How many weeks will it take to complete the project? 15wks D. Which activities have slack, and how much? Activity Slack C 3 F 1 G 1...
View Full Document

Ask a homework question - tutors are online