Resources and Resource Loading Knapp’s Backyard Grass Project Project Leader - Ron D. Knapp Activity Designation Time (Days) Resources Remove Rocks A 6 $432.00 Measure Backyard B 1 $ 72.00 Create Lists C .5 $ 36.00
Background image of page 1
This is the end of the preview. Sign up to access the rest of the document.

Unformatted text preview: Review Lists D .5 $ 36.00 Rent/Purchase Equipment/Supplies E 2 $144.00 Loosen Soil F 7 $504.00 Level Soil G 6 $432.00 Lay Sod H 7 $504.00 The estimated time is based on working 4 hours a day at $18 per hour....