Project Management Old Exam Questions Answers This Is a Constructed Project Network for problems 1-5 (The Top numbers for each box are the Early Start numbers and the Bottom numbers for each box are the Late Start numbers.) END 1. I. A-C-F is false because these three tasks are never connected as seen above. II. B-D-G is True because these three tasks are connected as seen above. III. B-E-F-G is True because these three tasks are connected as seen above. This leave you with the answer of D . 2. It would take 18 days as seen above highlighted in yellow. 3. Activity Late Start Early Start Slack Where the numbers came from is highlighted in red . 4. The late start time for C is shown in the above diagram in Green which is 11 . A 0 3 3 8 11 C 3 4 1 11 12 G 12 18 6 12 18 D 6 8 2 10 12 E 6 7 1 6 7 B 0 6 6 0 6 F 7 12 5 7 12 H 7 9 2 16 18 H 16 7 9
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
5. A). This wouldn’t work . This is because you need to use “the Early Start Time Rule” which states the ES time of an activity is equal to the largest EF times of all
Background image of page 2
This is the end of the preview. Sign up to access the rest of the document.

Page1 / 2

Project Management Questions 1-7 - Project Management Old...

This preview shows document pages 1 - 2. Sign up to view the full document.

View Full Document Right Arrow Icon
Ask a homework question - tutors are online