Net Present Value and Other Investment Criteria Chapter 9 1
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Good Decision Criteria We need to ask ourselves the following questions when evaluating decision criteria Does the decision rule adjust for the time value of money? Does the decision rule adjust for risk? Does the decision rule provide information on whether we are creating value for the firm? 2
Background image of page 2
Project Example Information You are looking at a new project and you have estimated the following cash flows: Year 0: CF = -165,000 Year 1: CF = 63,120; NI = 13,620 Year 2: CF = 70,800; NI = 3,300 Year 3: CF = 91,080; NI = 29,100 Average Book Value = 72,000 Your required return for assets of this risk is 12%. 3
Background image of page 3

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Net Present Value The difference between the market value of a project and its cost How much value is created from undertaking an investment? The first step is to estimate the expected future cash flows. The second step is to estimate the required return for projects of this risk level. The third step is to find the present value of the cash flows and subtract the initial 4
Background image of page 4
NPV – Decision Rule If the NPV is positive, accept the project A positive NPV means that the project is expected to add value to the firm and will therefore increase the wealth of the owners. Since our goal is to increase owner wealth, NPV is a direct measure of how well this project will meet our goal. 5
Background image of page 5

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Computing NPV for the Project Using the formulas: NPV = 63,120/(1.12) + 70,800/(1.12) 2 + 91,080/(1.12) 3 – 165,000 = 12,627.42 Using the calculator: – CF 0 = -165,000; C01 = 63,120; F01 = 1; C02 = 70,800; F02 = 1; C03 = 91,080; F03 = 1; NPV; I = 12; CPT NPV = 12,627.42 Do we accept or reject the project? 6
Background image of page 6
Decision Criteria Test - NPV Does the NPV rule account for the time value of money? Does the NPV rule account for the risk of the cash flows? Does the NPV rule provide an indication about the increase in value? Should we consider the NPV rule for our primary decision criteria? 7
Background image of page 7

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Payback Period How long does it take to get the initial cost back in a nominal sense? Computation Estimate the cash flows Subtract the future cash flows from the initial cost until the initial investment has been recovered Decision Rule – Accept if the payback period is less than some preset limit 8
Background image of page 8
Image of page 9
This is the end of the preview. Sign up to access the rest of the document.

Page1 / 34

Chap009s - Net Present Value and Other Investment Criteria...

This preview shows document pages 1 - 9. Sign up to view the full document.

View Full Document Right Arrow Icon
Ask a homework question - tutors are online