QUESTION 3 Zabeedah Sdn Bhd has a project that consists of six activities. The following table given the activities that must be accomplished in order to complete the project. Activity Immediate Predeccors Time (weeks) A - 8 B A 5 C B 6 D A 5 E B,D 7 F C,E 1 a) Contruct a project network for the problem E D F C B A
Image of page 1
b) Find the critical path. What is the expected project completion time? A-B-C-F = 8+5+6+1=20 A-B-E-F = 8+5+7+1=21 A-D-E-F = 8+5+7+1=21 Thus, the critical path is A-B-E-F and A-D-E-F The project completion time is 21 weeks.
Image of page 2
QUESTION 4 Task Effort (person- days) Ignore this column Duration (days) Dependencies T1
Image of page 3
Image of page 4
Image of page 5

You've reached the end of your free preview.

Want to read all 5 pages?

  • Fall '19
  • Project Management, Critical path, Critical path method, 60 days, 21¬†weeks, Zabeedah Sdn Bhd

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture

Stuck? We have tutors online 24/7 who can help you get unstuck.
A+ icon
Ask Expert Tutors You can ask You can ask You can ask (will expire )
Answers in as fast as 15 minutes