Character Reichart Assistant Project Manager  Project Manager Initial condition The program is out of schedule and expenditures were  excessive THE TROPHY PROJECT
Background image of page 2
Complain the functional manager   no use Report the project situation after  SIX  months   added corporate  staff  7:00am meeting every Monday morning   increased work load THE TROPHY PROJECT
Background image of page 3

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Problems  Project is behind schedule The functional manager hold the labor to do his own project Wasted  SIX  month The project is a year behind schedule after “six months” THE TROPHY PROJECT
Background image of page 4
Suggested solutions Better communication skill  Quick actions and priority setting Well corporate with the corporate staffs THE TROPHY PROJECT
Background image of page 5

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Assistant program manager’s suggestion Method: Computerize the problem   AND  Track the progress                      
Background image of page 6
Image of page 7
This is the end of the preview. Sign up to access the rest of the document.

Page1 / 18

Group 2 - Topic B - PROJETMANAGEMENT TheTrophyProject...

This preview shows document pages 1 - 7. Sign up to view the full document.

View Full Document Right Arrow Icon
Ask a homework question - tutors are online