ISE 441 Engineering Project Management Case Study Presentation Trouble in Paradise Lecturer: Dr. Joseph W. K. CHAN Presentation Date: 21 November
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
SCENARIO Trouble in Paradise
Background image of page 2
Contractor Finding A reward for becoming Acme Corporation's first PMP – assigned a new PMP, Wiley Coyote, the leadership A delay after submission – at least $100,000/ month A solicitation package has been done for attract a contractor
Background image of page 3

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Contractor Finding 8 companies prepared to bid based on that solicitation package Wiley Coyote just negotiate only with the low bidder, which has a significantly lower final cost than the other bidders Ima Roadrunner, handling the negotiations with Wiley It’s a contractor that Wiley never worked with previously
Background image of page 4
Contractor’s Information Critical information provided from contractors: All work accomplished by engineering Total burdened labor was 2000hrs at $120/hr Duration of project – approximately 6 months and would finished in 2006 (keep the same labor rate) Contractor’s overhead rate was 150% Engineering
Background image of page 5

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Contractor’s Information All of assigned workers would be at the same pay grade and signed full time workers Profit request 12.5% but subject to negotiation Ima Roadrunner’s salary included in overhaed structure No materials were required
Background image of page 6
Contractor’s Information Solicitation package identified a penalties for late delivery Ima argued that it is unfair…higher profit margin required to compensate for risks Ima request the profit margin: 12.5% >> 10% Both parties agreed to this deal
Background image of page 7

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Monthly Report Contract did not call for any type of “Earned value” Ima had very limited knowledge of earned value measurement and never used it
Background image of page 8
Image of page 9
This is the end of the preview. Sign up to access the rest of the document.

This note was uploaded on 10/02/2011 for the course ME ISE441 taught by Professor W.k. during the Spring '11 term at NYU Poly.

Page1 / 33

Group 11 - Topic H - ISE 441 Engineering Project Management...

This preview shows document pages 1 - 9. Sign up to view the full document.