Scheduling SpreadSheet

Scheduling SpreadSheet - (days) (days) A 14 20 1.42857143 B...

Info iconThis preview shows page 1. Sign up to view the full content.

View Full Document Right Arrow Icon
FCFS Job time Flow Time Due date Tardiness Job (days) (days) A 14 14 20 0 B 10 24 16 8 C 7 31 15 16 D 6 37 17 20 sum 37 106 44 Average FT 26.5 Average Tardiness 11 Makespan 37 Average WIP 2.8648648649 SPT D 6 6 17 0 C 7 13 15 0 B 10 23 16 7 A 14 37 20 17 37 79 68 24 Average FT 19.75 Average Tardiness 6 Makespan 37 Average WIP 2.1351351351 EDD C 7 7 15 0 B 10 17 16 1 D 6 23 17 6 A 14 37 20 17 37 84 68 24 Average FT 21 Average Tardiness 6 Makespan 37 Average WIP 2.2702702703 CR Job time Due date CR 0A Job
Background image of page 1
This is the end of the preview. Sign up to access the rest of the document.

Unformatted text preview: (days) (days) A 14 20 1.42857143 B 10 16 1.6 C 7 15 2.14285714 D 6 17 2.83333333 14C A B 10 16 0.2 C 7 15 0.14285714 D 6 17 0.5 21 B 10 16-0.5 C D 6 17-0.6666667 D B 10 16 B A 14 14 20 C 7 21 15 6 D 6 27 17 10 B 10 37 16 21 37 99 68 37 Average FT 24.75 Average Tardiness 9.25 Makespan 37 Average WIP 2.6756756757...
View Full Document

Ask a homework question - tutors are online