DS 412 Operations Management Spring 2010 Final Exam – Part I Prof Uday Note : 1. This is the take-home part of the exam. 2. Use MS Project to answer the question. 3. Your computer printouts must be turned in along with your in-class exam. 4. Please bring this question sheet to your in-class exam. A project is made up of several tasks, as shown in the table below.
Background image of page 1
This is the end of the preview. Sign up to access the rest of the document.

Unformatted text preview: Task Predecessor Duration (days) A-6 B-9 C A 8 D A 5 E B 4 F C 5 G D, E 7 The project is scheduled to begin on Monday, May17, 2010. Use MS Project to develop the project schedule. Obtain printouts of the Gantt Chart and the Network Diagram....